Capstone Reports Strong Production & Cash Operating Costs for the First Half of 2009
Wednesday, July 15, 2009 7:16 AM


VANCOUVER, July 15 /PRNewswire-FirstCall/ --

- 49.2 Million pounds of Copper in Concentrates With an Estimated Total Cash Cost(1) of US$0.93 per Pound of Payable Copper

Capstone Mining Corp. (CS: TSX) today announced its operating results for the three and six months ended June 30, 2009, with strong production and operating costs from its two operations, the Cozamin and Minto mines. Combined production totalled 23.1 and 49.2 million pounds of copper in concentrates in the second quarter and first six months, respectively, with additional significant by-products of lead, zinc, silver and gold. The total cash costs(1), net of estimated by-product credits and selling costs, were US$0.97 and US$0.93 per pound of payable copper produced, respectively.

'Capstone's two operations, the Cozamin and Minto mines, turned in another strong quarter, bringing first half production to 49.2 million pounds of copper in concentrates at a total cash cost of just US$0.93 per pound of payable copper,' said Stephen Quin, President & COO of Capstone Mining Corp. 'These results are a reflection of the quality of our operating teams and our assets.'

    -------------------------------------------------------------------------
                                              Q1 2009    Q2 2009    YTD 2009
    -------------------------------------------------------------------------
    Copper in concentrates
    (millions of pounds)
    -------------------------------------------------------------------------
      - Cozamin                                    9.8        9.9       19.7
    -------------------------------------------------------------------------
      - Minto                                     16.3       13.2       29.5
    -------------------------------------------------------------------------
    Total                                         26.1       23.1       49.2
    -------------------------------------------------------------------------
    -------------------------------------------------------------------------
    Total Cash Costs(1)
    (US$/lb)
    -------------------------------------------------------------------------
      - Cozamin                                  $1.00      $0.81      $0.90
    -------------------------------------------------------------------------
      - Minto((x))                               $0.86      $1.08      $0.96
    -------------------------------------------------------------------------
    Average                                      $0.91      $0.97      $0.93
    -------------------------------------------------------------------------
    ((x))  Minto's operating costs are adjusted to exclude mining of ore and
           waste not related to concentrate produced in the period, these
           costs are capitalized or inventoried in the financial statements,
           then expensed when the associated ore is processed.

Operational Highlights for the three and six months ended June 30, 2009

The following is a summary of operational highlights for Capstone during the second quarter and six months, respectively, ended June 30, 2009:

    - Production of 23.1 and 49.2 million pounds of contained copper,
      respectively, which is within previously reported guidance of 95-105
      million pounds of copper in concentrates for 2009.
    - By-product production of 3.3 and 5.7 million pounds of zinc, 2.3 and
      3.5 million pounds of lead and 455,566 and 875,520 ounces of silver in
      concentrates, for the second quarter and first six months,
      respectively. Final gold production is not available since assaying is
      done off site, but is estimated at 7,564 and 16,091 ounces.
    - Production of 22.2 and 47.4 million pounds of payable copper in
      concentrate for the second quarter and first six months of 2009,
      respectively.
    - Total cash cost per pound of payable copper produced(1) of US$0.97 and
      US$0.93 in the second quarter and first six months, respectively,
      versus previously published guidance of approximately US$1.00 per
      pound, which represents good progress in cost reductions since year end
      2008 as the expansions at both operations ramped up to design capacity
      (and more). Readers should note that some stripping in excess of that
      needed to sustain operations at the Minto Mine was inadvertently not
      capitalized in accordance with Capstone's (and formerly Sherwood's)
      policy in the first quarter of 2009 and costs for this period have been
      adjusted to make the first quarter comparable to all prior reporting
      periods.
    - Cozamin Mine results for the three and six months ended June 30, 2009,
      respectively, were:
    - Produced 9.9 and 19.7 million pounds of copper contained in
      concentrates, along with by-products of 3.3 and 5.7 million pounds of
      zinc, 2.3 and 3.5 million pounds of lead and 390,639 and 708,602 ounces
      of silver, respectively, for the second quarter and first six months of
      2009;
    - Processed 249,975 tonnes (2,741 tpd) and 498,300 tonnes (2,753 tpd) of
      ore averaging 1.92% and 1.94% copper, 1.01% and 0.91% zinc, 0.61% and
      0.47% lead, with 66 and 61 grams per tonne ('g/t') silver respectively,
      for the second quarter and first six months;
    - Total tonnes processed was below potential capacity of the mine because
      of (1) the five day shutdown related to Mexican government order aimed
      to slow the spread of the H1N1 flu virus and (2) slower than
      anticipated timing for bringing the high grade, large scale stopes on
      line, which resulted in the plant running out of feed on some days.
      When feed was available, the plant typically averaged 3,200 to 3,500tpd
      and achieved a single day throughput record of 4,088 tonnes processed
      in June.
    - Produced 17,595 and 36,056 dry metric tonnes ('dmt') of copper
      concentrate averaging 25.5% and 24.8%, 3,312 and 5,727 dmt of zinc
      concentrate averaging 45.5% and 45.2% and 1,500 and 2,282 dmt of lead
      concentrate averaging 70.5% and 69.4%;
    - Estimated total cash cost(1), net of estimated by-product credits and
      estimated selling costs, was US$0.81 and $0.90 per pound of payable
      copper produced; and
    - Announced a new life-of-mine plan and mineral reserve estimate for the
      Cozamin Mine on June 1, 2009. However, the process plant has
      Demonstrated sustained ability to exceed the assumptions used in the
      life of mine plan for throughput, copper recoveries and copper
      concentrate grades, suggesting potential for sustained higher than
      planned copper production, once the larger stopes discussed above are
      brought on line.
    - Minto Mine results for second quarter and the six months ended June 30,
      2009, respectively, were:
    - Produced 13.2 and 29.4 million pounds of copper contained in
      concentrates, along with by-product 64,927 and 166,918 ounces of silver
      and gold estimated at 7,564 and 16,091 ounces, respectively, for the
      second quarter and first six months;
    - Processed 267,254 tonnes (2,937 tpd) and 500,783 tonnes (2,767 tpd) of
      ore averaging 2.41% and 2.86% copper, an estimated 1.0g/t and 1.3g/t
      gold and 9.6g/t and 12.7g/t silver;
    - Plant throughput exceeded budget during the second quarter, and
      continued to trend upwards during the three month period, typically
      averaging 3,200 to 3,500 tonnes per operating day (excluding
      maintenance days) and reaching up to 3,700 tonnes processed on
      individual days;
    - Produced 14,667 and 31,950 dmt of copper concentrate averaging 40.8%
      and 41.6%;
    - Produced 12.7 and 28.5 million pounds of payable copper at an estimated
      total cash cost(1) of US$1.08 and $0.96 per pound of payable copper;
    - Copper production in Q2/09 was somewhat reduced as compared to Q1/09 as
      a result of excess spring run-off waters being diverted into the open
      pit to ensure no non-compliant discharges occurred, thereby restricting
      access to higher grade ore in the pit. This was anticipated in the
      budget for 2009 and milling operations continued uninterrupted from
      stockpiled material, albeit of somewhat lower grade than in prior
      months. However, freshet began a few days earlier than budgeted and
      more water than was anticipated was diverted into the pit.


(0)
No Comments
Post Comment
Name:  
Alert for new comments:
Your email:
Your Website:
Title:
Comments:
   
 
 
 
 
   
 

  
Related Press Releases
Advertisement
Popular Articles
Advertisement
Partner Center
Fundamental data is provided by Zacks Investment Research, market data is provided by AlphaTrade. , and Commentary and Press Releases provided by Quotemedia