VAL-D'OR, QC, Aug. 11 /CNW Telbec/ - Managements of J/V partners X-Ore Resources (TSXV: XOR) and First Gold Exploration (TSXV: EFG) are pleased to release a new NI43-101 compliant resource estimate for the Croinor property, located east of the town of Val-d'Or, Abitibi, Quebec.

This new resource estimate follows two years of intensive exploration drilling (approx. 13,000 metres) along the down dip and lateral extensions of the Croinor gold deposit. All results have been compiled and a re-interpretation of the entire deposit was performed. It is now believed that the deposit consists of numerous east-west elongated, shallowly north dipping and plunging mineralized shoots. This is a significant change from previous interpretations which indicated a series of discontinuous tabular structures. Individual mineralized shoot extends laterally from 50 metres up to 250 metres.

The following tables show the indicated resource and the measured resource for each vein and finally a summary of the indicated and measured resources at cut off grades of 5 g/t Au (base case for the resource estimate) and 7 g/t Au.

-------------------------------------------------------------------------
-------------------------------------------------------------------------
                         INDICATED RESOURCES
-------------------------------------------------------------------------
                        Cut-off 5,00 g/t Au        Cut-off 7,00 g/t Au
Zone              -------------------------------------------------------
                     Tonnes      gpt   Ounces   Tonnes      gpt   Ounces
-------------------------------------------------------------------------
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A2                   41,007    8.685   11,450   20,705   11.566    7,699
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A4                   17,469   10.468    5,879   11,136   13.316    4,767
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A5                   78,439   10.985   27,703   51,546   13.655   22,629
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A6                   74,650    9.346   22,432   39,922   12.447   15,975
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A11                   2,978   10.753    1,030    2,978   10.753    1,030
-------------------------------------------------------------------------
-------------------------------------------------------------------------
B1                   15,346    7.451    3,676    7,247    8.660    2,018
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C1                   61,496    9.225   18,239   39,073   11.236   14,115
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C2                   52,895    6.632   11,279    8,955   11.093    3,194
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C3                    8,679    5.530    1,543
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C4                   64,868    9.223   19,234   33,591   12.676   13,689
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C5                   35,044    6.628    7,468   11,515    8.482    3,140
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C6                   13,384   13.550    5,830    5,914   23.483    4,465
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C7                   15,507    9.342    4,658   15,049    9.434    4,565
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C8                   33,315     8.37    8,962   16,081    11.35    5,869
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C9                    9,305    6.181    1,849    2,836    7.223      659
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C10                   8,261    5.694    1,512
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C11                  18,877    6.833    4,147    5,750    8.880    1,642
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C12                   1,105    9.260      329    1,105    9.260      329
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C13                   1,144   10.950      403    1,144   10.950      403
-------------------------------------------------------------------------
-------------------------------------------------------------------------
D1                   13,046    5.475    2,296
-------------------------------------------------------------------------
-------------------------------------------------------------------------
D2                   73,574   10.402   24,605   30,540   17.038   16,729
-------------------------------------------------------------------------
-------------------------------------------------------------------------
D3                   79,023    9.928   25,223   40,394   14.136   18,358
-------------------------------------------------------------------------
-------------------------------------------------------------------------
D5                   63,624    9.802   20,050   40,154   12.502   16,140
-------------------------------------------------------------------------
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Total Indicated     783,036     9.13  229,799  385,636    12.70  157,416
-------------------------------------------------------------------------
-------------------------------------------------------------------------

-------------------------------------------------------------------------
-------------------------------------------------------------------------
                         MEASURED RESOURCES
-------------------------------------------------------------------------
                        Cut-off 5.00 g/t Au        Cut-off 7.00 g/t Au
-------------------------------------------------------------------------
Zone                 Tonnes      gpt   Ounces   Tonnes      gpt   Ounces
-------------------------------------------------------------------------
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A2                    1,029     7.47      247    1,029     7.47      247
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A4                    3,729    11.45    1,373    1,211    22.23      865
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A5                   13,037     9.27    3,883    8,551    11.04    3,035
-------------------------------------------------------------------------
-------------------------------------------------------------------------
A6                    9,038     7.47    2,171    1,816    13.00      759
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C2                    1,393     7.16      321    1,393     7.16      321
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C4                    1,881     7.22      437    1,211    22.23      865
-------------------------------------------------------------------------
-------------------------------------------------------------------------
C5                    1,085     5.27      184
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Total Measured       31,192     8.59    8,615   15,210    12.46    6,092
-------------------------------------------------------------------------
-------------------------------------------------------------------------

-------------------------------------------------------------------------
                   MEASURED and INDICATED RESOURCES
-------------------------------------------------------------------------
                        Cut-off 5.00 g/t Au        Cut-off 7.00 g/t Au
-------------------------------------------------------------------------
Category             Tonnes      gpt   Ounces   Tonnes      gpt   Ounces
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Total Measured       31,192     8.59    8,615   15,210    12.46    6,092
-------------------------------------------------------------------------
Total Indicated     783,036     9.13  229,799  385,636    12.70  157,416
-------------------------------------------------------------------------
-------------------------------------------------------------------------
Total               814,228     9.11  238,414  400,847    12.69  163,507
-------------------------------------------------------------------------
-------------------------------------------------------------------------

This new NI43-101 compliant resource estimate was performed by Pierre O'Dowd, P. Geo., independent consulting geologist and Qualified Person under NI43-101, based on the review of 832 diamond drill holes and all available technical information and previous report. The latter used the same geological parameters as the ones used by the firm InnovExplo for its 2005 estimate. The main parameters are:

- Minimum mining width of 1.8 m
- Polygons drawn on cross sections
- Polygons extend vertically and laterally to half the distance in
  between intercepts to a maximum of 20 metres
- Grade capped at 65 g/t Au
- Specific gravity of 2.8
- 5 g/t Au cut off as base case

This current estimate shows a 15% increase in the number of ounces of gold over the 2005 estimate (from 206,792 oz Au to 238,414 oz Au). As noted above, the average grade of the deposit, using 5 g/t Au cut off grade, was established at 9.11 g/t Au. A technical report presenting all information pertaining to the resource estimate, in conformity to Appendix NI43-101A1, will be filed shortly on Sedar within the prescribed time frame.

In recent news, it was announced that a scoping study was completed based on the 2005 resource estimate (July 15th 2009). The scoping study, performed by Golder and Associates of Val-d'Or, indicates that approximately 80,000 ounces of gold could potentially be extracted economically at Croinor. It is believed that, based on the new resource estimate and the new geological model for the mineralization, the economics of the deposit can be further improved. The partners, X-Ore and First Gold, have now started the procedures to obtain necessary permits to initiate the rehabilitation of the underground workings. Note that this scoping study is preliminary in nature and includes mineral resources that are not mineral reserves and do not have demonstrated economic viability. There is no certainty that the preliminary assessment will be realized as presented since certain engineering parameters related to construction, environment and rocks mechanics will have to be validated at the preproduction phase.

The revised model for the deposit opens a significant area of prospective ground which will hopefully increase resources while the development of the deposit is ongoing. Previous programs targeted the up and down dip extensions of known auriferous intercepts. Future drilling programs will target lateral extensions which exhibit a much better continuity.

Mr. Pierre O'Dowd (OGQ (number sign)668), a Qualified Person under NI 43-101 has revised and approved the technical content of this release. Mr. O'Dowd has accumulated more than 30 years in exploration experience in Canada and worldwide having worked with companies such as Falconbridge, Noranda, Cambior (Doyon Mine) before starting his consulting firm in 1995.

About X-Ore Resources Inc.

X-Ore Resources is a mineral exploration company with 16 properties located in known gold regions of Mexico and Canada, including the prolific Sierra Madre Gold Belt and the Val-d'Or region of Quebec.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release. This press release contains "forward-looking statements" not based on historical facts. Forward-looking statements express, as of the date of this press release, our estimates, forecast, projections, expectations and opinions as to future events or results. Forward-looking statements herein expressed are reasonable, but involve a number of risks and uncertainties, and there can be no assurance that such statements will prove to be accurate. Therefore, actual results and future events could differ materially from those anticipated in such statements. Factors that could cause results or events to differ materially from current expectations expressed or implied by the forward-looking statements include, but are not limited to, fluctuations in the market price of precious metals, mining industry risks, uncertainty as to calculation of mineral resources and requirements of additional financing and the capacity of the Company to obtain financing.

(Source: CNW )


(0)
No Comments
Post Comment
Name:  
Alert for new comments:
Your email:
Your Website:
Title:
Comments:
   
 
 
 
 
   
 

  
Related Press Releases
Advertisement
Popular Articles
Advertisement
Partner Center
Fundamental data is provided by Zacks Investment Research, market data is provided by AlphaTrade. , and Commentary and Press Releases provided by Quotemedia