VANCOUVER, Sept. 3 /CNW/ - Copper Mountain Mining Corporation ("CMMC" or
the "Company") reports that Merit Consultants International Inc.,Construction
Manager, for the Copper Mountain Project has awarded Gisborne Industrial
Construction Ltd the contract as General contractor to start mill foundation
work early this month subject to government approvals. The schedule provides
for the mill foundations to be completed this fall with steel being erected
early next spring. With the preliminary work completed this fall the mill
building will be fully enclosed by mid 2010 to allow equipment installations
to proceed to meet the planned mid 2011 production start.
The Project is an open pit porphyry copper mine that operated from 1972
to 1996 and over its life produced 1.74 billion pounds of copper, 9.1 million
ounces of silver and 730 thousand ounces of gold. The current resource is
estimated at 5 billion pounds of copper at a 0.15 % Cu cut-off. The resource
estimate incorporates data from over 4,400 historical drill holes totalling
approximately 400,000 metres, and 370 new drill holes, totalling 107,000
metres from the Company's 2007 and 2008 exploration programs.
Mr. O'Rourke, Chief Executive Officer of the Company stated: "Following
Mitsubishi Materials Corporation purchasing 25 percent of the project the new
Similco board approved the development schedule which has provided a major
step to the Company becoming a significant new mid tier copper producer. The
current economic conditions provide an ideal time to be developing a major
mine in British Columbia."
To date, site activities have been funded by the Company's equity
contributions and a $28.75 million line of credit from Mitsubishi, which
together have totalled almost $40 million. Long lead items have been ordered
with the SAG and ball mill manufacturing well underway to maintain the target
production schedule for mid 2011. Detailed engineering is progressing and site
geotechnical excavation for the concentrator is now complete. The office and
warehouse complex is now fully functional with power, heat, water, telephones,
internet, and sewerage. The Company currently has approximately 20 employees
currently engaged at the site on construction activities. It is estimated that
the project will provide employment for 200 construction workers at its peak
and the ongoing operations will create 257 full time positions. Over the 17
year life of the project, it is estimated that the mine will produce 1.47
billion pounds of Copper, 452,000 ounces of gold, and 4.5 million ounces of
silver.