(Source: North County Times)

By Paul Sisson, North County Times, Escondido, Calif.
Sep. 19--Nuclear regulators took no corrective action at San Onofre
Nuclear Generating Station after being briefed on weld defects by Southern
California Edison.
The utility met with Nuclear Regulatory Commission project manager James
R. Hall early this week to explain why the defects, found in a pair of massive
steam generators being manufactured in Japan, are not also present in a set of
identical components that have already been delivered to San Onofre.
Edison will soon begin its most extensive upgrade at San Onofre when it
installs the generators inside one of the plant's two concrete containment
domes. A second, identical operation is scheduled for October 2010.
Hall said the work should start on schedule.
"We're only a few weeks away from the outage at San Onofre," Hall said.
"There isn't any deliberation within the NRC to hold up the steam generator
replacement as it has been planned."
A steam generator looks like a giant inverted milk bottle and is filled
with nearly 10,000 thin metal tubes. Water heated by the plant's nuclear
reaction runs through the tubes, which are surrounded by cool water that turns
to steam and spins the plant's turbines, creating electricity. The old
generators must be replaced, at a cost of $680 million, because their tubes
have begun to crack, reducing each reactor's ability to make steam and
generate juice.
In the end, the difference between the two sets of monoliths comes down
to grinding versus gouging.
Edison, the plant's majority owner, notified regulators in late August
that two 640-ton steam generators still being manufactured by Mitsubishi Heavy
Industries in Kobe, Japan, had developed cracks in a weld that connects a
5-inch-thick steel plate to each unit's larger steel superstructure. The
plates are critical both for supporting the generators' innards and also for
separating flows of coolant that circulate through each reactor's core, where
highly-radioactive fuel rods sit.
When installing the plate in the first set of generators, workers used
grinders to prepare metal surfaces for the welds, which have not cracked under
testing, according to Edison's report. However, workers used a special metal
gouging apparatus to prepare the second set, and that machinery left behind
carbon deposits that eventually caused the weld to become brittle and crack.
Workers have already begun repairing the defects and will finish doing so
before the units are hauled, via ship, across the Pacific Ocean to San Onofre.
Hall said the NRC will still inspect every aspect of the steam generator
replacement project as it goes forward in October. The procedure requires
cutting a large hole in the side of one of the plant's two concrete
containment domes, because existing access hatches are too small.
An identical procedure will follow in 2010 for the second operating
reactor.
-----
To see more of the North County Times, or to subscribe to the newspaper, go to
http://www.nctimes.com.
Copyright (c) 2009, North County Times, Escondido, Calif.
Distributed by McClatchy-Tribune Information Services.
For reprints, email tmsreprints@permissionsgroup.com, call 800-374-7985 or 847-635-6550, send a fax to 847-635-6968, or write to The Permissions Group Inc., 1247 Milwaukee Ave., Suite 303, Glenview, IL 60025, USA.
EIX,
A service of YellowBrix, Inc.