(Source: MARKETWIRE)

Paladin Energy Ltd ("Paladin" or "the Company") (TSX: PDN)(ASX: PDN)
is pleased to provide its Quarterly Activities Report for the three
month period ended 30 September, 2009.
HIGHLIGHTS
- September quarter overall production of 744,188lb - slight increase
from last quarter.
-- Langer Heinrich to achieve Stage 2 production of 3.7Mlb pa for Dec
09 quarter.
-- Kayelekera ramp-up behind schedule, however, design production of
3.3Mlb pa still on target for March 2010 quarter.
- Financial Year 2010 guidance revised to a range of 5.6Mlb to 6.1Mlb
due to slower production ramp-up at Langer Heinrich and Kayelekera.
- Sales of 703,000lb at an average price of US$54.5/lb for revenue of
US$38.3M for quarter.
- Major new production expansion plans for Africa (increasing from
8.5Mlb pa to 13.8Mlb pa) to clearly establish Paladin as a Tier 1
producer.
-- Stage 4 Langer Heinrich expansion targeting 10Mlb pa (includes
1Mlb heap leach) with nameplate production by mid 2014.
-- Kayelekera optimisation to 3.8Mlb pa by mid 2013.
- US$374M private placement completed.
OVERALL SAFETY
The Kayelekera Mine suffered two fatalities in August and early
October both related to mobile equipment/vehicles. The second
fatality involved a bus overturning with 20 employees on board, which
resulted in several additional injuries.
Paladin management has taken immediate actions to audit and, where
necessary, improve safety throughout the organisation. Both
Kayelekera and Langer Heinrich will initiate the National
Occupational Safety Association (NOSA) system by mid November. NOSA,
which combined with the strengthening safety culture at Langer
Heinrich, is expected to consolidate the necessary improvements in
safety performance.
Evidence clearly points to vehicle traffic as a major safety risk for
both operations and Paladin Senior Management is committed to
developing an appropriate safety regime also focussing on the
Company's global transportation requirements.
LANGER HEINRICH MINE, Namibia
Production
For the quarter, Langer Heinrich produced 654,516lb U3O8 (Stage 1
nameplate capacity), which was less than that of the previous
quarter, due to numerous interruptions from Stage 2 integration
(plant tie-ins and equipment commissioning) and low equipment
availability on the front end of the plant. At quarter end, all major
Stage 2 integration had been completed and ramp-up to the Stage 2
production level was in progress. Although significant improvements
to the scrubber units on the plant front end have been completed in
the past, the 40% increase in tonnage necessitated adjustments to
their operation and maintenance schedules, particularly for the
liners. Additionally, the two new leach tanks in the second leach
circuit required a replacement of faulty agitators.
Recent production figures indicate that Stage 2 levels are now almost
being realised with the October production forecast to be
approximately 275,000lb U3O8 (90% of Stage 2 nameplate design).
Sales
Sales for the quarter were 703,000lb U3O8 at a value of US$38.3M,
representing an average sales price of US$54.48/lb U3O8.
Mining
Mining has continued in both Pit A and Pit D. A new pit, Pit F, which
lays adjacent to the temporary tailings facility, will be prepared
for mining early in 2010 to facilitate the planned tailings
management systems and to provide an optimal blend of feed material
to the plant.
The plant ore feed during the quarter was as follows:
-------------------------------
July Aug Sept Total
----------------------------------------------------------------------------
Crushed tonnes,
dry 130,436 141,434 151,086 422,956
----------------------------------------------------------------------------
Feed Grade, ppm 896 939 917 918
----------------------------------------------------------------------------
Process Plant
Process efficiencies were affected by the stopping and starting of
the plant as Stage 2 equipment was brought on line and the processes
fine-tuned. Despite these disruptions, an overall efficiency of 78.5%
was achieved for the quarter. Scrub efficiency dropped from previous
high levels but is expected to improve by mid October once the
remaining upgrades to the screens are completed. Leach efficiency for
the quarter was excellent (93.2%) despite the issues with the new
agitators. Iron exchange (IX) efficiency was briefly affected by the
carryover of solids from prepared reagent solutions that were not
completely dissolved.
Tailings
Current emphasis is on the design and construction of extensions to
the berm walls of the existing temporary tailings facility. The
design of the first in-pit new tailings facility to the west of the
plant is in progress with construction expected to commence in early
2010.
Preparation for the establishment of Pit F, adjacent to the temporary
tailings facility, commenced during the quarter. Once mined out, this
pit will be utilised for flood water control and rain water
harvesting, thereby releasing Pit A and Pit B for tailings storage
much earlier than previously planned.
Stage 2 Upgrade Progress
Despite some initial problems with scrubber availability, screen
efficiency and leach agitators, the plant feed tonnage was increased
during the quarter, particularly in the last half of September. Daily
tonnages of over 6,000t per day have been achieved for 60% of this
time (Stage 2 design is 6,453tpd) reaching close to 7,000t on
occasions.
All outstanding items for Stage 2 commissioning have now been brought
online, with the exception of a second dryer, which has no
significance to current plant production. Difficulties experienced
during the commissioning period included delays to front end
installation, dust controls and pumping and piping issues from the
new counter current decantation (CCD) thickeners.
All these issues have been addressed and resolved during the quarter
and the Stage 2 production target is now expected to be achieved for
this current December quarter.
Stage 3 Upgrade
In accordance with previously released information, the final design
parameters have been set for a Stage 3 expansion on the following
basis:
- Nominal production to increase to 5.2Mlb pa U3O8 (an increase of
1.5Mlb pa or 40% from the nominal Stage 2 level of 3.7Mlb pa)
- Target completion date set for the December quarter 2010
- Capital cost estimated at US$71M
- No significant additional infrastructure
The flowsheet will involve a number of significant upgrades across
the processing plant, particularly a second crushing & scrubbing feed
line with increases to the existing screening plant, an additional
leach tank (with heat exchangers etc), two additional CCD thickeners
and expansion of the ion exchange circuit.
The Stage 2 expansion has already incorporated capacity for the Stage
3 expansion in the pre-leach thickening, precipitation, product
drying and some reagent dosing facilities.
No upgrade to the water supply, nor expansion of the power supply
facilities are necessary with ample grid and generator capacities
already available.
Exploration Activity EPL3500
Exploration drilling on EPL3500, west of the Langer Heinrich Mining
Lease, was undertaken during the quarter. A total of 27 RC holes, for
2,199m were drilled. All holes were downhole gamma logged and
equivalent U3O8 grade values have been calculated.
The drilling succeeded in extending the Langer Heinrich mineralised
palaeochannel by approximately 300m further west and the
mineralisation appears to be still open in this direction. Better
intersections included:
-----------------------------------------------------------------------
-----
Hole Depth From Depth To Intersection Grade (ppm eU3O8)
----------------------------------------------------------------------------
EPL3 58 81 23 278
----------------------------------------------------------------------------
EPL4 54 62 8 738
----------------------------------------------------------------------------
EPL6 68 74 7 334
----------------------------------------------------------------------------
EPL7 66 75 7 258
----------------------------------------------------------------------------
EPL10 51 60 9 614
----------------------------------------------------------------------------
The intersections shown above were calculated using a cut off grade
of 100ppm and a maximum width of internal waste of 1m. All holes were
drilled on a nominal 100m x 50m grid.
KAYELEKERA URANIUM PROJECT, Malawi
Production
Kayelekera production of 89,672lb for the quarter was hampered by a
slower than expected ramp-up in July and August, however September
results were improved and this upward trend should continue towards
the anticipated nameplate production rates in the March 2010 quarter.
Most significantly, the entire Resin-In-Pulp (RIP) circuit has now
proven to be effective and with a number of mechanical availability
issues rectified, the ramp-up should continue on-track.
The first shipment of product was trucked from Kayelekera to the
Walvis Bay port (Namibia) in August, with a second shipment of two
containers leaving site on 12 October. Sulphuric acid continues to be
trucked to site as commissioning of the acid plant has been delayed
(acid production is expected to commence in late October). Project
Development
Construction of the sulphuric acid plant was completed during the
quarter. Acid production is expected to commence by the end of
October after some initial commissioning delays.
The construction workforce has been progressively demobilised with
only a small workforce retained to complete work on the Tailings
Storage Facility (TSF) and acid plant completion.
The Malawi Government's road building contractor continues to work on
two bridges and some culverts/drains in the first 13km section of the
M26 public road that was recently sealed. Work is on schedule to be
completed in the next quarter. Major roadworks on the final 19km
section to the mine access road have commenced.
Operations - Commissioning and Ramp-up
Ramp-up over the past quarter has been slower than anticipated due to
mechanical availability of certain equipment (numerous pumps) and
pipe work, which have been identified and are in the process of being
replaced.
At quarter end, the Kayelekera employee workforce totaled 234 of
which 71% were Malawian. The contractor workforce totaled 641 persons
with the mining contractor, the largest single group, having 191
people.
Mining
A total of 246,400t of ore grading 1,364ppm U3O8 and 264,800t of
waste were removed from the pit in this quarter. Currently there is
about 700,000t of ore either on the Run of Mine (ROM) pad or exposed
in the pit. The mining fleet, not required for open pit mining, has
been mobilised to assist with the construction of the outstanding TSF
wall.
Process Plant
The front end of the plant is still in the process of ramp-up with a
temporary semi-mobile jaw crusher planned for installation to augment
crushing requirements.