logo


We Energies' Project Starts Creating Power: Coal-Fired Plant in Oak Creek Being Tested
Friday, October 30, 2009 3:51 AM


(Source: The Milwaukee Journal Sentinel)trackingBy Thomas Content, Milwaukee Journal Sentinel

Oct. 30--The most expensive construction project in state history, We Energies' new $2.3 billion coal-fired plant in Oak Creek, has begun generating power, having reached several construction milestones in recent months, the company's chairman said Thursday.

The plant consists of two coal-fired boilers next to an older coal plant on Lake Michigan. The first of the two boilers began burning coal earlier this month and has been running at 25% of maximum power in recent days, said Gale Klappa, chairman and chief executive of Wisconsin Energy Corp., the parent of We Energies.

Bechtel Power Corp., the contractor on the project, also has made progress on building the second boiler, which is now 74% complete, Klappa said.

The project's cost is roughly double the combined cost of building Miller Park and rebuilding the Marquette Interchange.

"What we're seeing at Oak Creek is significant progress in the past three months," Klappa said.

Bechtel is now testing the plant at 25% of its full output, and plans to ramp that up to 50% within the next few days.

The Oak Creek project was hit with construction delays and cost overruns that are the subject of a nearly $500 million dispute between We Energies and Bechtel. The companies tried to resolve the dispute through mediation, but the case is now in the hands of a three-person arbitration panel. A decision is expected late next year or in 2011, Klappa said.

Bechtel claimed that harsh weather conditions and labor problems contributed to construction delays and extra costs for the project. We Energies objects to most of the claims but agreed that weather conditions played a role in some of the delays, Klappa said.

Under the original timeline, the first boiler was scheduled to open in September, but Bechtel said it would finish the project by the end of December. The contractor is slightly behind schedule at this point but optimistic the project will be done by year's end, according to Klappa.

When completed, the two boilers will generate 1,230 megawatts of power -- enough to serve more than 1 million homes.

Construction of the plant began in June 2005, after the state Supreme Court rejected legal challenges to the plant filed by S.C. Johnson & Son Inc. and environmental groups.

The environmental groups objected to adding coal-fired energy at a time of growing concern about emissions linked to global warming.




(0)
No Comments
Post Comment
Name:  
Alert for new comments:
Your email:
Your Website:
Title:
Comments:
   
 
 
 
 
   
 

  
Related Press Releases
Advertisement
Popular Articles
Advertisement
Partner Center
Fundamental data is provided by Zacks Investment Research, market data is provided by AlphaTrade. , and Commentary and Press Releases provided by Quotemedia