(Source: Milwaukee Journal Sentinel)

By THOMAS CONTENT
By THOMAS CONTENT
The most expensive construction project in state history, We
Energies' new $2.3 billion coal-fired plant in Oak Creek, has begun
generating power, having reached several construction milestones in
recent months, the company's chairman said Thursday.
The plant consists of two coal-fired boilers next to an older
coal plant on Lake Michigan. The first of the two boilers began
burning coal earlier this month and has been running at 25% of
maximum power in recent days, said Gale Klappa, chairman and chief
executive of Wisconsin Energy Corp., the parent of We Energies.
Bechtel Power Corp., the contractor on the project, also has made
progress on building the second boiler, which is now 74% complete,
Klappa said.
The project's cost is roughly double the combined cost of
building Miller Park and rebuilding the Marquette Interchange.
"What we're seeing at Oak Creek is significant progress in the
past three months," Klappa said.
Bechtel is now testing the plant at 25% of its full output, and
plans to ramp that up to 50% within the next few days.
The Oak Creek project was hit with construction delays and cost
overruns that are the subject of a nearly $500 million dispute
between We Energies and Bechtel. The companies tried to resolve the
dispute through mediation, but the case is now in the hands of a
three-person arbitration panel. A decision is expected late next
year or in 2011, Klappa said.
Bechtel claimed that harsh weather conditions and labor problems
contributed to construction delays and extra costs for the project.
We Energies objects to most of the claims but agreed that weather
conditions played a role in some of the delays, Klappa said.
Under the original timeline, the first boiler was scheduled to
open in September, but Bechtel said it would finish the project by
the end of December. The contractor is slightly behind schedule at
this point but optimistic the project will be done by year's end,
according to Klappa.
When completed, the two boilers will generate 1,230 megawatts of
power -- enough to serve more than 1 million homes.
Construction of the plant began in June 2005, after the state
Supreme Court rejected legal challenges to the plant filed by S.C.
Johnson & Son Inc. and environmental groups.
The environmental groups objected to adding coal-fired energy at
a time of growing concern about emissions linked to global warming.
To address those concerns and meet the state's renewable power
mandate, We Energies has retired an old coal-fired power plant in
Port Washington and announced plans for new wind farms, biomass
energy projects and an expansion in solar power.
The company opened the largest wind farm in the state last year
and has proposed an even bigger project, the Glacier Hills Wind
Park, in Columbia County.
The second Oak Creek coal boiler is scheduled for completion at
the end of August.
We Energies customers have seen costs linked to the project send
electricity bills higher since 2004. The main drivers of big jumps
in customers' electric bills since that time have been costs linked
to power plant construction and fuel costs.
Power plant construction costs are a factor in the 2010 price
increase proposed by We Energies that the state Public Service
Commission will vote on in November. That proposal would raise
customers' bills 7% from current levels, taking into account a drop
in rates earlier this year.
Also proposed to be included in rates are costs linked to a
settlement of lawsuits filed by groups that challenged the legality
of water permits for the water intake systems for the Oak Creek
plant.
We Energies and its utility partners, Madison Gas & Electric Co.
and WPPI Energy, decided that adding cooling towers, instead of
relying on the cooling system already built, could have added more
than $1 billion to the price tag of the project. The settlement was
projected to cost the three utilities $105 million over 20 years.
Customers including the Wisconsin Industrial Energy Group, which
represents large industrial power users, have objected to raising
rates to pay for the legal settlement.
Copyright 2009, Journal Sentinel Inc. All rights reserved. (Note:
This notice does not apply to those news items already copyrighted
and received through wire services or other media.)
(c) 2009 Milwaukee Journal Sentinel. Provided by ProQuest LLC. All rights Reserved.
A service of YellowBrix, Inc.