(Source: MARKETWIRE)

B2Gold Corp. (TSX: BTO) ("B2Gold" or the "Company"), announces the
following update in the affairs of the Company, including:
- Construction of the Orosi Mine in Nicaragua is 95% complete and
remains on schedule for completion and the commencement of production
in late November 2009. Open pit mining has commenced. The Orosi Mine
is projected to produce an average of 80,000 to 90,000 ounces of gold
per year with an initial mine life of seven years
- With both the Orosi and Limon mines operating, B2Gold's gold
production for 2010 is projected to be approximately 120,000 to
130,000 ounces with estimated cash costs of approximately $490 to
$500 per ounce at Orosi and approximately $545 to $560 per ounce at
Limon. Both mines are debt free and un-hedged
- The Company has signed a commitment letter for a US$20 million
secured revolving credit facility with Macquarie Bank Limited
("Macquarie")
- At the Limon Mine in Nicaragua, one of the three labour unions has
triggered an illegal strike and shut down production. The Ministry of
Labour of the Government of Nicaragua has declared the strike to be
illegal. The Company is in discussions to resolve this dispute and
expects to recommence production shortly
- Exploration drilling is scheduled to recommence on the Kupol West
property's Moroshka west zone, in Far East Russia (the Kupol East and
West properties are a joint venture with B2Gold, Kinross Gold
Corporation ("Kinross") and the government of Chukotka, Russia)
- B2Gold's exploration team has generated numerous exploration
targets around the Limon and Orosi mines and on other joint venture
properties in Nicaragua
Orosi Mine
The Orosi mine construction is 95% complete and remains on target for
the completion of construction and the commencement of production in
late November. The power supply is complete and is connected to the
national power grid and the initial tailings storage facility is
ready for start-up. Initial capacity of the mill is expected to be
3,500 tonnes of ore per day and will ramp up to 5,500 tonnes of ore
per day once the second ball mill is installed in the second quarter
of 2010. The Company is projecting gold production of approximately
84,000 ounces from an average grade of 1.81 grams per tonne ("g/t")
gold for 2010. Contract open pit mining has commenced with a new
mining fleet.
The total construction cost for Orosi is now estimated at
approximately US$62 million. This is an increase of approximately $7
million, or 13% from the Company's previous estimate. The primary
reasons for the increased construction costs are: higher costs to
excavate the tailings dam due to heavier than usual rains in June,
July and August; a change in routing of the new power line, due to
surface rights access issues; and additional changes to the mill to
accommodate the second ball mill which will increase throughput from
3,500 tonnes per day to 5,500 tonnes per day.
B2Gold owns a 100% interest in the Orosi open pit gold mine, which
commenced operating as a heap leach mine in 1996. Operations were
suspended in the first quarter of 2007 after a re-evaluation of the
project indicated that gold recoveries could be improved from
approximately 40% from heap leaching to over 90% using a conventional
milling operation. Once in commercial production, the Orosi Mine will
have an initial seven year mine life and is expected to produce
approximately 80,000 to 90,000 ounces of gold annually at an
estimated cash cost of approximately $465 per ounce. The Orosi Mine
has excellent exploration targets adjacent to the mine over a 20 km
belt. Excellent potential exists to increase the reserves, resources
and the mine life. The Orosi Mine is 100% un-hedged and debt free.
Limon Mine
B2Gold holds a 95% interest in the Limon Mine, with the remaining 5%
being held by Inversiones Mineras S.A., a holding company
representing unionized mine workers in Nicaragua. The Limon Mine
concession includes numerous epithermal gold-quartz veins and has
been in operation as an underground and open pit gold mine since
1941. To date the Limon Mine has produced approximately three million
ounces of gold. The current operation is a 1,000 tonne per day
underground and open pit mine. The Limon Mine currently has a mine
life of 3.5 years with projected average annual production of
approximately 43,000 ounces of gold annually at an estimated cash
cost of approximately $550 per ounce. B2Gold has identified several
exploration targets at the Limon Mine site and the Company expects to
continue to add reserves to the Limon Mine increasing the mine life.
Gold production at the Limon Mine was recently halted by an illegal
strike, initiated by the Pedro Roque Blandon Union that represents
46% of the unionized workers at Limon. The Limon Mine has a long
history of labour disputes, which the Company had expected to cease
after signing a collective bargaining agreement on July 3rd, 2009
with all three Limon unions.