(Source: MARKETWIRE)

Silver Standard Resources Inc. (TSX: SSO)(NASDAQ: SSRI) reports the
following principal project updates and financial highlights from the
company's third quarter of 2009. Effective January 1, 2009, the
company adopted the U.S. dollar as its reporting currency and all
figures are in U.S. dollars, unless otherwise noted.
Update on Pirquitas Mine
The company began open pit pre-stripping in July 2008 as well as
developing mill and support teams in preparation for continuous
operations. This mining activity exposed oxide and transitional ore
during the first quarter of 2009 and the ore continued to be
stockpiled while the historical jig tailings were fed through the
silver circuit during the third quarter. A total of 13.6 million
tonnes of waste and 499,600 tonnes of oxide and transitional ore have
been mined as at September 30, 2009.
The silver circuit operated during the third quarter, and in
September operating time averaged 93% over 22 consecutive days prior
to a scheduled four-day shutdown as the plant proved its mechanical
and electrical reliability. The plant feed to the end of the quarter
was comprised of 139,000 tonnes of historical jig tailings ranging in
grade from 90 grams/tonne to 465 grams/tonne for an average grade of
166 grams/tonne.
As envisioned in the feasibility study, the historical jig tailings
were to provide material to prove the operation of the facility.The
metallurgical performance from the jig tailings has been
disappointing as a result of the variation in head grade and
oxidation precipitates within the jig tailings. This has resulted in
inconsistent silver recovery ranging from 30% to 60% and concentrate
grades ranging from 900 grams of silver/tonne to in excess of 5
kilograms of silver/tonne. The company shipped 56,388 ounces of
silver in concentrates during the third quarter.
Pirquitas is now feeding oxide ore from the open pit into the mill
and expects to achieve silver recoveries of approximately 30% from
this mill feed. The mill will continue to operate on oxide and
transitional ore until the first quarter of 2010 when sulphide ore
from the open pit will be introduced as mill feed.
As a consequence, Pirquitas is now expected to produce approximately
1 to 1.5 million ounces of silver in 2009 depending on the
consistency of the oxide and transitional ore silver recoveries. Test
work on the open pit sulphide ore has confirmed the feasibility study
results, and the company plans to provide estimated silver production
for 2010 later in the year as production schedules are finalized for
the coming year.
During the quarter, approximately $22.0 million was incurred on
construction and mining equipment at the Pirquitas project in
Argentina. To September 30, 2009, $239 million has been expended for
the construction of the plant facilities and equipment compared to
the previous estimate of $233 million. The $239 million includes an
additional $5 million expended during ramp-up for enhancements made
to the original plant design to optimize the silver flotation
circuit.With the continuing construction and commissioning of the
plant, the company incurred $48.7 million in pre-operating costs for
the nine months ended September 30, 2009, of which $18.7 million were
incurred during the third quarter.