(Source: Canada Newswire)

ARBN 108 066 986
TORONTO, Nov. 13 /CNW/ - Equinox Minerals Limited (TSX and ASX
symbol: "EQN") ("Equinox" or the "Company") today released its
results of operations and financial condition for the three and nine
months ended September 30, 2009, and its financial position as at
September 30, 2009.
All currencies specified in this press release are denominated in
U.S. dollars.
HIGHLIGHTS FOR THE QUARTER
--------------------------
- Copper production increased 15% over Q209 and 26% over Q109,
with
28,111 tonnes of copper produced at an average (C1) operating
cost of
$1.46 per pound;
- Operating profit increased 77% over Q209 with the achievement
of
$64.1 million operating profit for the three month period ended
September 30, 2009 (commercial production commenced April 1,
2009);
- Operating profit was subsequently offset by non-cash
derivative
instrument losses resulting from the rising copper price leading
to a
net loss position, after tax, of $56.3 million, primarily related
to
the remaining hedge book being marked to market at the current
strengthening copper price. Revenue was positively impacted by
the
strengthening copper price;
- Realized copper price, net of smelter treatment charges, was
$2.58
per pound and 16,632 tonnes of payable copper provisionally
priced at
$2.79 per pound ($6,153 per tonne) remain subject to final
pricing
adjustment during Q409;
- Total material movement increased by 44% compared to Q209 and
ore
mined increased by 33% compared to Q209;
- Lower metallurgical recoveries continued to impact production
due to
the proportion of transitional ore processed. Orebody studies by
consultants Golder & Associates show that the Malundwe resource
reconciliations are consistent with the original mine design.
These
studies also confirm original estimates that the transitional ore
constitutes about 5% of the orebody;
- Mining of the uranium zones at Valeria South and Valeria
North within
the Malundwe pit has produced a stockpile of 1.94mt (at) 1,044
ppm
uranium and 0.81% copper to the end of Q309;
- Pit preparation has been substantially enhanced for the
forthcoming
2009/2010 wet season;
- Hitachi has agreed to mobilize an additional five x EH4500
dump
trucks in order to expedite the recovery of lost availability
hours
on the existing fleet. These additional trucks are scheduled to
be on
site by mid 2010;
- Equinox took delivery of an additional Caterpillar light
mining fleet
including 16 x 40-tonne dump trucks, 5 x 100-tonne dump trucks, 2
x
excavators and 3 x bulldozers, which are being used primarily to
accelerate stripping of weathered material;
---------------------------------------------------
Performance Three months ended Nine
months ended
September 30 September 30
---------------------------------------------------
2009 2008 2009 2008
-----------------------------------------------------------------
--------
Gross sales
(in thousands) $170,798 n/a $298,531
n/a
Net income/(loss)
(in thousands) ($56,266) ($680) ($155,598)
($10,616)
Earnings/(loss) per
share ($0.08) ($0.00) ($0.24)
($0.09)
Payable copper in
tonnes 26,465 n/a 50,100
n/a
Payable copper in
pounds 58,344,166 n/a 110,450,470
n/a
Average (C1)
operating cost $1.46 n/a $1.46
n/a
Realized copper price
per pound (net of
smelter treatment
charges) $2.58 n/a $2.38
n/a
Cash and cash
equivalents (in
thousands) $119,862 $51,327 $119,862
$51,327
Number of shares
outstanding 704,618,212 592,959,858 704,618,212
592,959,858
-----------------------------------------------------------------
--------
At the end of Q309, the Company had 16,632 tonnes of payable
copper provisionally priced at $2.79 per pound ($6,153 per tonne)
remain subject to final pricing adjustment during the fourth
quarter.
OVERALL PERFORMANCE
-------------------
Operations
----------
An operating profit was achieved by the Company for the three
month period ending September 30, 2009. An operating profit of $64.1
million was generated at the Lumwana Mine during the quarter, a 77%
improvement on Q209. The operating profit was subsequently offset by
a non-cash hedging instrument loss of $88.4 million related to the
remaining hedge position which no longer qualifies for hedge
accounting, leading to a net loss position, after tax, for the
quarter of $56.3 million or $0.08 per share.
During the quarter, the Lumwana mine continued to ramp up both
the mine and process plant operations. Ore processed at the Lumwana
Mine for the quarter was 3.82 million dry metric tonnes of ore,
producing 59,652 dry metric tonnes of concentrate at an average
copper grade of approximately 47.1%. This represents an increase in
processed tonnes of 8.0% from the prior quarter due to continued
improvement from the mining activities, resulting in copper produced
in concentrate of 28,111 tonnes (61.97 million pounds) at an average
(C1) operating cost of $1.46 per pound.
Mine productivity continued to improve during the quarter, with
ore mined increasing to 4.02 million tonnes, an increase of 33%
compared to Q209 and total material movement increasing 44% to 29.3
million tonnes. The Malundwe Orebody at Lumwana is currently
operating from four sub-pits which will ultimately merge into one
large pit. Ore production to date has primarily been from the
'Starter' and '1E' pits. As additional sub-pits are opened up along
the strike of the ore body, further transitional (mixed sulphide-
oxide) ore continues to be encountered. However, as further mining
in Malundwe exposes more consistent sulphide ore, the negative
impact of mixed ores on recoveries will diminish.
While ore production continued to increase from last quarter,
actions being taken to further improve mine production include the
following:
- Improving availability of the Hitachi mine truck and shovel
mobile
equipment fleet. Although the general trend is improving over the
year, the availability needs to further improve and be maintained
to
meet production targets.
- Hitachi is responsible for the maintenance and repair
contract on the
Hitachi fleet at Lumwana and is initiating measures to ensure
that
contract availability rates are achieved and to make up hours of
availability lost to date. Hitachi has agreed to mobilize an
additional five EH 4500 dump trucks (240t) in order to expedite
the
recovery of lost availability on the existing fleet. These
additional
trucks are scheduled to be on site by mid 2010. Subsequent to the
making up of lost hours, Equinox will purchase those trucks at
their
depreciated value. This is envisaged to occur in mid 2011. Other
improvement initiatives include Hitachi Japan taking direct
control
of the management of the maintenance and repair contract,
implementation of a new operating structure, increasing spare
parts
stock levels for Hitachi equipment and increasing personnel and
resources.
- The purchase of additional mining fleet equipment during the
quarter:
- Equinox took delivery of an additional Caterpillar light
fleet
comprising 16 x 40-tonne articulated dump trucks, 5 x 100-tonne
dump trucks; 2 x excavators and 3 x bulldozers. This fleet is
primarily being utilized to accelerate stripping of weathered
material. Sub-contractor light fleets are also operating for
civil works and stripping; and
- The Company also purchased an additional 3 x Sandvik D45K
drilling rigs to accelerate drill and blast operations in the
pit, which will enhance material movement.
- The Equinox team continued to work with mining productivity
experts
Jamieson Group to assist our site management to improve
productivity
performance in the mine. While excellent gains have been made we
continue to see further room for improvement.
- The second stage of the trolley assist infrastructure was
commissioned during the quarter, providing trolley access from
the
main ramp to the Starter pit. Utilization of the extended trolley
lines will improve ramp speeds and consequently reduce cycle
times,
as well as reducing the hybrid diesel-electric truck operating
costs.
- Wet season preparations are well advanced, following the
experience
of mining at Lumwana during the 2008/2009 wet season. Wet season
pit
preparations have been substantially enhanced for the forthcoming
2009/2010 wet season with:
- diversion channels to control surface water ingress into the
pit;
- substantial sumps excavated for the collection of in-pit
water;
- pumping capacity doubled since 2008; and
- all main ramps and roads have been sheeted and surfaced to
improve road conditions, particularly during wet periods.
Lower metallurgical recoveries continued to impact production
during the quarter due to the proportion of transitional ore being
processed. For Lumwana ore, recoveries in transition material
typically range between 50 - 60% whereas those in sulphide ore
typically range between 90 - 95%. Orebody studies by consultants
Golder & Associates show that the Malundwe resource reconciliations
are consistent with the original estimate. The Malundwe reserve
reconciliations are showing good correlation with metal content,
although grade dilution is occurring as a consequence of using
higher bench heights of 8m as opposed to the 4m used in the original
mine plan. Although further transitional ore will be encountered in
the weathering zone of each new pit to be developed at Lumwana, the
proportion of transition ore to sulphide ore is reducing as the pits
deepen along the length of the orebody.
Mining of the uranium zones at Valeria South and Valeria North
within the Malundwe pit has produced a stockpile of 1.94mt (at)
1,044 ppm uranium and 0.81% copper to the end of Q309. This copper-
uranium ore is being diverted away from the copper concentrator, and
is being classified as "waste" to the copper project. This uranium-
rich copper ore stockpile may be treated at a later date, if and
when the Company builds a uranium plant.
The 20 Mtpa processing plant continues to perform to expectation
and is capable of producing in excess of its design capacity based
on achieved through put rates to date.
Lumwana Mine Production Statistics
-----------------------------------------------------------------
--------
Q1 Q2 Q3 Total
Production Statistic Measure 2009 2009 2009
to-date
-----------------------------------------------------------------
--------
Total mine material
movement Tonnes (m) 8.88 20.80 29.3
59.57
Ore mined Tonnes (m) 1.84 3.03 4.02
8.89
Ore processed Tonnes (m) 2.88 3.03 3.82
9.73
Head grade Copper % 0.93 0.98 0.92
0.94
Copper recovery Copper % 83 82 80
82
Concentrate grade Copper % 39 39 47
42
Copper produced in
concentrate Tonnes 22,263 24,413 28,111
74,787
Copper produced in
concentrate Pounds (m) 49.08 53.82 61.97
164.87
Average (C1)
operating cost Per Pound - $1.46 $1.46
$1.46
-----------------------------------------------------------------
--------
Production Guidance
Management believes that based on the work underway in
preparation for the forthcoming wet season, a continuing focus on
mining fleet productivity, the commissioning of further trolley-
assist infrastructure to help improve truck cycle times and the
increasing exposure of new sulphide ore zones, that the fourth
quarter of 2009, subject to wet season conditions, should
demonstrate additional improvement on quarterly production to date.
As such, management estimates production guidance for the full 2009
calendar year should be between 105,000 and 110,000 tonnes (231 -
242 million pounds) of copper metal in concentrates at an average
estimated (C1) operating cost of between $1.35 and $1.50 per pound.
Management believes that it is taking appropriate remediation
action to meet the challenges specified in this report.
Expansion and Optimization Plans
Significant opportunities exist at the Lumwana Mine following the
completion of ramp up to further expand and optimize the
concentrator and mine throughput rate, to assess and evaluate the
additional near mine deposits discovered to date and to develop the
Lumwana Mine uranium resource. Equinox will continue to assess these
opportunities for expansion and organic growth at the Lumwana Mine.
Equinox has also completed the uranium feasibility study ("UFS")
investigating the onsite treatment of discrete and high grade
uranium mineralization contained within the Lumwana Mine copper
pitshells. The UFS has confirmed the potential viability of onsite
uranium treatment. Should Equinox be successful in negotiating
viable uranium offtake agreements and securing the requisite project
capital financing, the Company estimates plant construction to take
approximately 18 to 24 months. The decision to proceed with the
development of the Lumwana Uranium Project will depend, subject to
Board approval, on a number of factors including satisfactory
financing and offtake terms being negotiated. The stockpiling of
Lumwana Mine uranium ore is ongoing and to the end of Q309 the
stockpile totaled 1.94mt (at) 1,044 ppm uranium and 0.81% copper.
Equinox will continue to review and assess opportunities for
organic growth and expansion, and corporate opportunities to grow
the Company.
ZESCO Update
The Company previously announced that it is in dispute with ZESCO
Limited ("ZESCO"), Zambia's national power supply utility, over
electricity charges believed by ZESCO to be incurred by the Company
between 2007 and 2008. ZESCO has claimed invoice values totaling
$9.0 million for the period up to December 31, 2008. However, based
on legal advice, the Company has determined a value of $2.0 million
is payable based on the terms of the contract. The Company disputes
ZESCO's claim, and has paid $2.0 million to ZESCO while conducting
negotiations in an effort to resolve the matter. The Zambian
Government has replaced the board and Chief Executive Officer of
ZESCO, the ZESCO Notice of Termination has been withdrawn and
discussions continue with the new management of ZESCO. Equinox
believes that the matter can be resolved in a reasonable manner.
Zambian Tax Legislation
The Government of the Republic of Zambia ("GRZ") enacted on April
1, 2008, a number of changes to the Zambian tax regime, particularly
in relation to mining companies. This includes changes to the tax
treatment that would increase corporate tax from 25% to 30%, the
mining royalty from 0.6% to 3%, and a number of other proposed
additional imposts including a "variable profit tax", a "windfall
tax" and treatment of hedging income as separate source income.
On January 30, 2009, the Minister of Finance of the GRZ announced
changes to the 2009 Budget which include the abolition of a number
of changes enacted in 2008, including the removal of the hedging
activity quarantine provisions. The 2009 changes took effect on
April 1, 2009. The Company has applied the tax changes from the
effective date.
In 2005 the Company entered into a Development Agreement with GRZ
for its Lumwana Mine which provides LMC with a 10 year stability
period in the regulatory environment, including taxation, and rights
of independent arbitration in the event of any dispute. Following
local and international legal advice, the Company believes that its
Development Agreement overrides the current changes to the Zambian
tax regime. Until it has resolved the uncertainty surrounding the
application of the Development Agreement, the company has measured
in the current year its taxation balances on the basis of the
enacted legislation.
If the Company had calculated its taxation related balance based
on the terms of the Development Agreement the royalty expense for
the nine months ended September 30, 2009 would have reduced by $6.1
million and the income tax benefit for the nine months ended
September 30, 2009 would have increased by $11.2 million. The
retained earnings loss position at September 30, 2009 would have
reduced by $8.0 million.
Offtake Update
During the quarter, concentrate delivery was predominantly
directed to Chambishi Copper Smelter Limited ("CCS") and the Konkola
Copper Mines Plc ("KCM") smelter at Nchanga on the Zambian
Copperbelt.
Town Development
The Lumwana town development continues to advance with 637 houses
completed to the end of Q309. The commercial and retail
developments, including the recently opened Lumwana supermarket, are
advancing and a self-sustaining modern town environment is being
developed.
Corporate Activities
--------------------
In September 2009, the Company's subsidiary, Lumwana Mining
Company Limited ("LMC") exercised its option to extinguish the right
held by Phelps Dodge Mining (Zambia) Limited ("PD Zambia") to
receive a 1% Lumwana Mine net smelter return royalty under the
purchase and sale agreement (the "Purchase and Sale Agreement")
dated December 8, 2004 between PD Zambia and the Company.
Between August 1999 and June 2003, the Company earned a 51%
interest in Lumwana as a result of expending $10 million and
completing a bankable feasibility study. Under the Purchase and Sale
Agreement, the Company acquired the remaining 49% interest in the
Lumwana Mine.
The Purchase and Sale Agreement provided that PD Zambia would
retain the right to a 1% Lumwana Mine net smelter royalty which
could be terminated by the Company at its option under certain
conditions.