ITCTransmission Celebrates Start of Construction of Thumb Loop High-Voltage Transmission Line

Friday, June 29, 2012 9:00 AM

NOVI, Mich., June 29, 2012 /PRNewswire/-- ITCTransmission, a wholly-owned subsidiary of ITC Holdings Corp., the nation's largest independent electricity transmission company, today celebrated the start of construction of its 140-mile Thumb Loop high-voltage transmission line with an event aimed at recognizing the cooperative efforts of contractors, vendors, local officials and community leaders in Michigan's Thumb area to advance the project. 

ITC hosted the celebration outside its new Bauer substation at the western end of the 345,000-volt line in Tuscola County. Bauer is one of four new substations being built for the project. Construction is just getting underway on the first transmission line segment, a 62-mile segment from Bauer to the new Rapson substation site in Huron County, east of Bad Axe. The Tuscola County section will cover approximately 25 miles. 

"The Thumb Loop project is the largest single project we have ever undertaken and is critical to supporting transmission upgrades in this region of Michigan," said Gregory Ioanidis, president of ITC Michigan.  "Our Michigan-based contractor, M.J. Electric, is off to a great start with the project. We're also enjoying excellent support from local vendors and suppliers who are providing support services and products. We appreciate the ongoing cooperation of local officials and community leaders. They're all important to the success of the Thumb Loop project."

ITC estimates that the current phase of Thumb Loop construction is providing more than 70 direct employment jobs, including contractors, vendors and suppliers, many of which are local. The area economy benefits from the demand for motel rooms, restaurants, concrete, hardware, fuel, gravel and trucking services, among other needs.

Line construction on the Phase 1 segment will continue into 2013. Crews are drilling and pouring concrete pole foundations and installing steel monopole and lattice structures. Stringing of the conductors (wires) will begin later in the summer. ITC has worked with landowners along the route to negotiate easement agreements and establish access points for equipment and materials along the 200-foot-wide transmission corridor. 

About the Thumb Loop Project

The Thumb Loop project consists of approximately 140 miles of double-circuit 345,000 volt
(345 kV) transmission lines and four new substations.  It will serve as the "backbone" of a system designed to meet the identified maximum wind energy potential of the Thumb region and will be capable of supporting a maximum capacity of about 5,000 MW.  As an important link in the high-voltage transmission system in Michigan and the region, it also will contribute to reducing congestion, improving system reliability and facilitating wholesale market competition. Additional lines and facilities will be needed in the future as wind generators go into service and connect to the backbone system.  The project will be constructed in stages. Construction on the first segment, the western side of the loop from Tuscola County to Huron County, began in the second quarter of 2012 and will finish in late 2013. The remainder is targeted for completion by 2015. For more information about the Thumb Loop project, please visit www.itctransco.com.

About ITCTransmission

International Transmission Company (d/b/a ITCTransmission) is a wholly-owned subsidiary of ITC Holdings Corp., the nation's largest independent electricity transmission company. Based in Novi, Michigan, ITCTransmission owns, operates and maintains approximately 2,800 circuit miles of transmission line in southeast Michigan, serving a population of 5.1 million.  For more information, please visit http://www.itctransco.com.

About ITC Holdings Corp.

ITC Holdings Corp. (NYSE: ITC) is the nation's largest independent electricity transmission company.  Based in Novi, Mich., ITC invests in the electric transmission grid to improve system reliability, expand access to markets, lower the overall cost of delivered energy and allow new generating resources to interconnect to its transmission systems.  ITC's regulated operating subsidiaries include ITCTransmission, Michigan Electric Transmission Company, ITC Midwest and ITC Great Plains.  Through these subsidiaries, ITC owns and operates high-voltage transmission facilities in Michigan, Iowa, Minnesota, Illinois, Missouri and Kansas, serving a combined peak load exceeding 26,000 megawatts along 15,000 circuit miles of transmission line.  Through ITC Grid Development and its subsidiaries, the company also focuses on expansion in areas where significant transmission system improvements are needed.  For more information, please visit: http://www.itc-holdings.com.

SOURCE ITC Holdings Corp.

(Source: PR Newswire )
(Source: Quotemedia)

Follow iStockAnalyst on Twitter Follow iStockAnalyst on Twitter
Subscribe to Email Alerts
Advertisement
Post Comment -- Login is required to post message
Name:  
Alert for new comments:
Your email:
Your Website:
Title:
Comments:
 




Fundamental data is provided by Zacks Investment Research, and Commentary, news and Press Releases provided by YellowBrix and Quotemedia.
All information provided "as is" for informational purposes only, not intended for trading purposes or advice. iStockAnalyst.com is not an investment adviser and does not provide, endorse or review any information or data contained herein.
The blog articles are opinions by respective blogger. By using this site you are agreeing to terms and conditions posted on respective bloggers' website.
The postings/comments on the site may or may not be from reliable sources. Neither iStockAnalyst nor any of its independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. You are solely responsible for the investment decisions made by you and the consequences resulting therefrom. By accessing the iStockAnalyst.com site, you agree not to redistribute the information found therein.
The sector scan is based on 15-30 minutes delayed data. The Pattern scan is based on EOD data.