(under IFRS and all amounts in US dollars unless otherwise stated)
TSX: AXY
VANCOUVER, Nov. 14, 2012 /CNW/ - Alterra Power Corp. (TSX: AXY)
("Alterra") today provided an update on its operations and reported its
financial and operating results for the three months ended September
30, 2012 ("the current quarter"). For further information on these
results please see Alterra's Unaudited Condensed Consolidated Interim
Financial Statements ("consolidated results") and Management's
Discussion and Analysis.
Under IFRS, Alterra consolidates 100% of the HS Orka and Soda Lake
operations, while Alterra's interests in the Toba Montrose run of river
hydro facility and the Dokie 1 wind facility are accounted for as
equity investments. In certain statements in this news release,
Alterra's results are disclosed as Alterra's "net interest", which
means the effective portion of results that Alterra would have reported
if each of HS Orka (66.6%), Toba Montrose (40%), Dokie 1 (51%) and Soda
Lake (100%) had been reported in accordance with Alterra's actual share
of ownership at September 30, 2012 and for the three months then
ended. Management believes that net interest reporting provides the
clearest view of the Company's performance.
Highlights for the current quarter and subsequently include:
-
Power production from Alterra's six power plants of 762,570 MWh was
ahead of plan (102% of budget) for the quarter, as strong performances
at the Toba Montrose run of river hydro plant and the Svartsengi and
Reykjanes geothermal plants offset lower than budget production from
the Soda Lake geothermal plant and Dokie 1 wind farm. Alterra's net
interest in generation totalled 399,007 MWh.
-
Alterra's net interest in revenue for the quarter was $29.2 million and
net interest in EBITDA was $17.8 million.
-
Alterra entered into an agreement with Energy Development Corporation
("EDC"), a Philippines-based global leader in the geothermal power
industry, which may be advanced into partnerships for the development
of the Mariposa geothermal project in Chile and for the development of
five geothermal concessions in Peru. The terms allow EDC to earn 70%
interests in the partnerships in return for funding the next $58.3
million of expenditures at Mariposa and the next $8.0 million in Peru.
-
The Company entered into a development phase agreement with a contractor
to perform project optimization and design work for the Upper Toba
hydro project, and is planning to commence construction in the second
quarter of 2013. Other project advancements included drilling and
seismic testing for the powerhouse and intake locations.
John Carson, Alterra's CEO, said, "I'm pleased with the progress we made
this period with both the Upper Toba hydro project and the South
American geothermal assets. Our advancement of all our other
development assets is underpinned by our continued on-track operating
performance, which is a tribute to our operating teams."
Financial Results
The results for Toba Montrose and Dokie 1 have been included since May
13, 2011, the date of their acquisition. The results for the current
quarter are now fully comparable to the comparative quarter ended
September 30, 2011 ("the comparative quarter").
The following table shows Alterra's net interest in selected operating
and financial results for the current quarter, in addition to key
financial information extracted from the consolidated results.
(expressed in thousands of US dollars, except for production)
|
|
|
|
|
|
September 30, 2012
|
September 30, 2011
|
|
|
Net Interest Total
|
Consolidated Results Total
|
Net Interest Total
|
Consolidated Results Total
|
|
Production (MWh)
|
399,007
|
310,215
|
441,409
|
304,710
|
|
Total Revenue
|
$ 29,244
|
$ 13,326
|
$ 36,079
|
$ 17,009
|
|
Gross Profit
|
15,743
|
2,189
|
20,207
|
4,856
|
|
EBITDA (a), (b) |
17,764
|
19,808
|
20,456
|
22,104
|
|
Total Assets
|
|
729,044
|
|
723,149
|
|
Total Liabilities
|
|
341,230
|
|
360,681
|
|
Cash and Cash Equivalents
|
|
42,288
|
|
24,693
|
|
Working Capital
|
|
28,793
|
|
3,881
|
Net interest for the three months ended September 30, 2012 by entity has
been broken out below:
|
|
|
|
|
|
|
|
|
|
HS Orka (66.6%)
|
Toba Montrose (40%)
|
Dokie Wind (51%)
|
Soda Lake (100%)
|
Exploration and Head Office
|
Net Interest Total
|
|
Production (MWh)
|
198,406
|
154,208
|
34,085
|
12,308
|
-
|
399,007
|
|
Total Revenue
|
$ 8,338
|
$ 16,210
|
$ 3,890
|
$ 806
|
$ -
|
$ 29,244
|
|
Gross Profit
|
2,439
|
13,259
|
1,518
|
(1,473)
|
-
|
15,743
|
|
EBITDA (a), (b) |
4,077
|
14,092
|
2,429
|
(998)
|
(1,836)
|
17,764
|
|
Long Term Debt
|
96,139
|
189,988
|
93,133
|
-
|
120,744
|
500,004
|
|
Cash Interest Paid
|
759
|
2,973
|
1,549
|
-
|
19
|
5,300
|
(a) EBITDA is defined by Alterra as earnings before interest, taxes, foreign
exchange, depreciation and amortization, as well as before deductions
for other gains and losses, amortization of below market contracts, and
value assigned to options granted less share of income (loss) of equity
accounted investees plus the Company's interest in EBITDA of its equity
accounted investees. Alterra discloses EBITDA as it is a measure used
by analysts and by management to evaluate Alterra's performance. As
EBITDA is a non-IFRS measure, it may not be comparable to EBITDA
calculated by others. In addition, as EBITDA is not a substitute for
net earnings, readers should consider net earnings in evaluating
Alterra's performance.
|
|
|
|
(b)Income for the period to EBITDA reconciliation
|
|
|
|
|
|
Three months ended
|
|
|
|
|
September 30, 2012
|
|
Income for the period
|
|
|
$
|
14,669
|
|
Adjustments:
|
|
|
|
|
|
Income tax expense
|
|
|
|
3,373
|
|
Share of income of equity investees
|
|
|
|
(10,374)
|
|
Share of EBITDA of equity investees
|
|
|
|
17,323
|
|
Other gains and losses
|
|
|
|
(10,034)
|
|
Finance costs
|
|
|
|
2,162
|
|
Finance income
|
|
|
|
(535)
|
|
Amortization of below market contracts
|
|
|
|
(566)
|
|
Amortization, depreciation, depletion and accretion
|
|
|
3,582
|
|
Stock based compensation
|
|
|
|
208
|
|
EBITDA
|
|
|
$
|
19,808
|
Alterra's net interest in EBITDA for the current quarter totaled $17.8
million compared to $20.5 million in the comparative quarter while net
interest in revenue was $29.2 million compared to $36.1 in the
comparative quarter. The decrease in both was primarily due to a
reduction in our net interest in HS Orka from 75% to 66.6%, devaluation
of the Icelandic Krona and aluminium linked power sales contracts,
lower than expected winds at Dokie 1 and higher costs of sales at Soda
Lake for pump repairs and maintenance.
Consolidated revenue for the current quarter was $13.3 million compared
to $17.0 million in the comparative quarter. Gross profit was $2.2
million for the current quarter, compared to $4.9 million for the
comparative quarter, due to lower revenue offset by lower production
costs.
Alterra recorded consolidated net income of $14.7 million for the
current quarter compared to a net loss of $11.4 million for the
comparative quarter. The improvement in the quarter is largely
attributable to $1.4 million of savings in general and administrative
costs as well as a number of non-cash items including:
-
A net positive non-cash change in the fair value of bonds and embedded
derivatives of $29.5 million, related primarily to changes in the
forecast future price of aluminum.
-
A non-cash improvement in foreign exchange gain (loss) of $7.4 million,
with the current quarter's $2.9 million foreign exchange gain being
contrasted to the comparative quarter's loss of $4.5 million.
At September 30, 2012, Alterra had consolidated cash and cash
equivalents of $42.3 million (December 31, 2011: $22.2 million) and our
net interest in cash and cash equivalents was $35.0 million. Alterra
ended the quarter with consolidated working capital of $28.8 million
(December 31, 2011: $4.6 million), $32.6 million on a net interest
basis. The increase in both cash and working capital occurred in the
first quarter of 2012 and was primarily due to the investment of $37.5
million in HS Orka by Alterra's pension fund partners (Jarðvarmi slhf)
and the receipt of the US government grant of $2.1 million by Soda
Lake.
Iceland Operations (66.6% Interest)
The 100 MW Reykjanes plant generated 182,431 MWh of electricity (104% of
budget), and the 72 MW Svartsengi plant generated 115,476 MWh of
electricity (110% of budget), and continued to supply thermal energy
for district heating.
Toba Montrose Operations (40% Interest)
The 146 MW East Toba River and 89 MW Montrose Creek run of river hydro
plants generated 385,521 MWh of electricity, or 101% of budget.
Toba Montrose achieved a new daily production record in July of 5,504
MWh, and generated in excess of 5,000 MWh on five days in the current
quarter.
Dokie 1 Operations (51% Interest)
The 144 MW Dokie 1 wind farm generated 71,909 MWh of electricity for the
current quarter, or 93% of budget. The shortfall was primarily due to
lower than expected wind.
Soda Lake Operations (100% Interest)
The 15 MW Soda Lake geothermal plant generated a net 12,308 MWh of
electricity for the current quarter, or 80% of budget. The lower than
expected performance was primarily attributable to higher than average
ambient summer temperatures in Nevada, which reduced the plant's net
production.
Expansion and Development Projects
Alterra has agreed to purchase for approximately $6.0 million, subject
to a number of closing conditions, 10% of a 50 MW portfolio of five
photovoltaic solar facilities being built in Ontario ("ABW Solar") by
First Solar, Inc. Alterra will serve as the managing partner for the
project. Construction has begun on the project and completion is
expected by the end of 2012 for three of the facilities and by the end
of January 2013 for the remaining two facilities. Long term fixed rate
project debt financing arrangements are expected to be completed before
the end of 2012.
Alterra is finalizing plant design of the Upper Toba Valley run of river
hydro project and plans to commence construction in second quarter of
2013. Geotechnical investigations including drilling and seismic
testing were performed in the current quarter at the powerhouse and
intake locations on the Jimmie Creek and Upper Toba sites. The Company
has entered into a development phase agreement with a contractor to
perform project optimization and preliminary design work. The proposed
facility would share much of the infrastructure already in place for
Toba Montrose, and is currently configured for up to 124 MW of capacity
and annual generation of up to 345,000 MWh, though final size and
projected output are currently being optimized. The project has a 40
year PPA in place with BC Hydro.
Preparations continue for the two expansions at the Reykjanes plant that
would increase capacity to 180 MW and annual average generation by
approximately 700,000 MWh. The key issues remaining prior to
construction are to conclude the ongoing PPA amendment negotiations and
to obtain project financing.
Alterra holds a 51% interest in a planned expansion of the Dokie 1 wind
farm ("Dokie 2") with projected additions to capacity of up to 156 MW
and annual production of up to 357,000 MWh. During the current quarter
Alterra continued to advance the resource assessment and planning of
the project.
Exploration Projects
Alterra signed an agreement with EDC that outlines the terms of
partnerships for the development of the Mariposa geothermal project in
Chile and further exploration at five of Alterra's geothermal
concessions in Peru (the South American projects). If EDC advances
into a formal arrangement then they will be entitled to earn 70%
interests in the partnerships by funding the next $58.3 million in
project expenditures at Mariposa and the next $8.0 million in project
expenditures on the five Peruvian concessions.
Alterra continued to advance its early stage geothermal exploration
projects in Italy, British Columbia and Peru with field work, data
assessment and continued community consultations.
Alterra also continued to advance its Bute Inlet project and other early
stage run of river and pumped storage hydro projects in British
Columbia.
Outlook
Ross Beaty, Alterra's Chairman, said, "The third quarter was a good one
for our operating assets. We have a strong clean energy platform in
geothermal, wind and hydro and will soon add a solar business through
ABW Solar. We are busy planning for more growth in 2013 through our
Upper Toba and Iceland expansions, while also reviewing acquisition and
divestment opportunities that result from today's market conditions. I
look forward to executing on these opportunities in the near future."
Alterra Power will host a conference call to discuss financial and
operating results on: Thursday, November 15, 2012 at 11:30 am ET (8:30 am PT).
North American participants dial 1-888-231-8191 and International
participants dial
1-647-427-7450, the conference ID is 6008 9943. The call will also be
broadcast live
on the Internet at http://www.newswire.ca/en/webcast/detail/1061061/1153511. The
call will be available for replay until November 22 by dialing
1-416-849-0833 and
entering replay pin number 6008 9943.
|
Cautionary Note regarding Forward-Looking Statements and Information
Certain statements included in this news release may contain information
that is forward-looking within the meaning of certain securities laws,
including information and statements regarding prospective results of
operations, financial position, cash flows or growth potential. These
statements are based on factors or assumptions that were applied in
drawing a conclusion or making a forecast or projection, including
assumptions based on historical trends, current conditions and expected
future developments. Since forward-looking statements relate to future
events and conditions, by their very nature they require making
assumptions and involve inherent risks and uncertainties. Alterra
cautions that although it is believed that the assumptions are
reasonable in the circumstances, these risks and uncertainties give
rise to the possibility that actual results may differ materially from
the expectations set out in the forward-looking statements. Material
risk factors include those set out in the management's discussion and
analysis section of Alterra's most recent annual report and quarterly
report, and in Alterra's Annual Information Form. Given these risks,
undue reliance should not be placed on these forward-looking
statements, which apply only as of their dates. Other than as
specifically required by law, Alterra undertakes no obligation to
update any forward-looking statements or information to reflect new
information, subsequent or otherwise.
SOURCE: Alterra Power Corp.