TSX-V: ORC.A, ORC.B
TORTOLA, British Virgin Islands, Nov. 29, 2012 /CNW/ - Orca Exploration
Group Inc ("Orca Exploration" or the "Company") announces its results
for the quarter ended 30 September 2012.
Highlights
-
Running at the maximum plant and pipeline capacity, the Company
delivered Additional Gas sales volumes averaging 57.5 MMcfd for the
quarter, up 6% over Q2 (Q3 2011: 56.1 MMcfd).
-
A 23% increase in Industrial Gas sales volumes and a 28% increase in
Power Gas prices, together with a higher revenue share from cost
recovery combined to deliver record funds from operations before
working capital changes of US$14.1 million (US$0.41 per share) for the
quarter - a 44% increase over Q2 (US$9.9 million or $0.28 per share)
and 170% over Q3 2011 ($5.3 million or $0.15 per share).
-
Profit after tax for the quarter was down 75% from Q2 to US$1.3 million
or US$0.04 per share (Q2 2012: US$5.2 million or US$0.15) a result of
writing off US$7.5 million in costs associated with the La Tosca Italy
exploration well.
-
Working capital at the end of the quarter of $37.7 million including
cash of $23.3 million, down 2% and up 15% respectively over Q2,
primarily the result of drilling SS-11 offset by the drawdown of US$6.0
million in a new bank financing and the receipt of some TANESCO
payments during the quarter.
-
Some progress has been made regarding TANESCO payments - the Company
received US$13.2 million from the state utility during the quarter and
a further US$9.5 million since the end of the quarter. At the end of
Q3, the TANESCO receivable stood at US$31.2 million (including arrears
of US$26.8 million), up 5% from US$29.6 million (including arrears of
US$25.6 million) at the end of Q2. As at the date of this report
TANESCO arrears total US$21.7 million.
-
The new production well SS-11 was brought onstream 3 October and is
currently producing approximately 38 MMcfd of natural gas.
-
The SS-9 well, which was producing approximately 30 MMcfd, was planned
to be shut in and used only as spare capacity until SS-12 could be
drilled. During the quarter, rising casing annulus pressures resulting
from a tubing leak dictated that SS-9 be permanently suspended. With a
similar rise in casing annulus pressure, a decision was taken to
suspend SS-3 to ensure continued safe operations in the field.
-
In August, the Government issued an order to redirect all gas volumes to
the state utility until 31 December 2012 to aid in emergency power
generation. The Company in collaboration with the Government identified
a solution which provided TANESCO with sufficient volumes of gas
without compromising the Company's Industrial Gas customers.
-
Construction has commenced on the pipeline infrastructure expansion
project in Tanzania - the government has stated that the 532km
pipeline and its associated facilities are expected to be completed and
commissioned in 18 months. The Company is developing a plan with TPDC
which would double deliverability to 200MMscfd by the time the
infrastructure expansion is complete. Any commitments by the Company to
proceed are subject to resolution of TANESCO payments, GNT issues,
satisfactory commercial arrangements and financing.
-
On 1st November 2012, the Government of Tanzania issued a draft natural
gas policy for review and consultation among the various stakeholders.
The draft policy contemplates a restructuring of TPDC, strategic
participation throughout the upstream, midstream and downstream
sectors, ownership and control over gas infrastructure and setting
domestic natural gas prices. The Company has been asked to submit its
views on the draft policy.
-
Drilling of the La Tosca well in the Longastrino exploration block in
the Po Valley, Northern Italy commenced on 7 August 2012; the well
reached total depth on 27 August and has been plugged and abandoned
having encountered gas shows. Orca has earned a 70% working interest
and, subject to government approval, operatorship of the block. The
Company intends to review the technical and drilling data to determine
whether or not to continue exploration on the block.
.
|
Financial and Operating Highlights
|
|
|
|
|
|
THREE MONTHS ENDED OR AS AT
|
|
NINE MONTHS ENDED OR AS AT
|
|
30 Sep 2012
|
30 Sep 2011
|
Change
|
|
30 Sep 2012
|
30 Sep 2011
|
Change
|
Financial (US$'000 except where otherwise stated)
|
|
|
|
|
|
|
|
|
Revenue
|
22,425
|
10,457
|
114%
|
|
56,545
|
28,393
|
99%
|
|
Profit before taxation
|
6,310
|
1,289
|
389%
|
|
25,136
|
6,660
|
277%
|
|
Operating netback (US$/mcf)
|
3.14
|
1.78
|
76%
|
|
2.75
|
1.88
|
46%
|
|
Cash and cash equivalents
|
23,289
|
42,632
|
(45%)
|
|
23,289
|
42,632
|
(45%)
|
|
Working capital
|
37,730
|
58,369
|
(35%)
|
|
37,730
|
58,369
|
(35%)
|
|
Shareholders' equity
|
120,204
|
101,563
|
18%
|
|
120,204
|
101,563
|
18%
|
|
Earnings per share - basic (US$)
|
0.04
|
0.00
|
n/a
|
|
0.37
|
0.08
|
363%
|
|
Earnings per share - diluted (US$)
|
0.04
|
0.00
|
n/a
|
|
0.36
|
0.08
|
350%
|
|
Funds flow from operating activities
|
14,379
|
5,323
|
170%
|
|
34,250
|
13,562
|
153%
|
|
Funds per share from operating activities - basic (US$)
|
0.42
|
0.15
|
193%
|
|
0.99
|
0.39
|
154%
|
|
Funds per share from operating activities - diluted (US$)
|
0.41
|
0.15
|
186%
|
|
0.97
|
0.38
|
155%
|
|
Net cash flows from operating activities
|
9,088
|
(2,457)
|
n/a
|
|
21,430
|
3,181
|
574%
|
|
Net cash flows per share from operating activities - basic (US$)
|
0.26
|
(0.07)
|
n/a
|
|
0.62
|
0.09
|
578%
|
|
Net cash flows per share from operating activities - diluted (US$)
|
0.26
|
(0.07)
|
n/a
|
|
0.61
|
0.09
|
581%
|
|
Outstanding Shares ('000)
|
|
|
|
|
|
|
|
|
Class A shares
|
1,751
|
1,751
|
0%
|
|
1,751
|
1,751
|
0%
|
|
Class B shares
|
32,743
|
32,939
|
(1%)
|
|
32,743
|
32,939
|
(1%)
|
|
Options
|
2,172
|
2,807
|
(23%)
|
|
2,172
|
2,807
|
(23%)
|
|
Operating
|
|
|
|
|
|
|
|
|
Additional Gas sold (MMcf) - industrial
|
1,022
|
719
|
42%
|
|
2,686
|
1,957
|
37%
|
|
Additional Gas sold (MMcf) - power
|
4,270
|
4,442
|
(4%)
|
|
12,415
|
10,201
|
22%
|
|
Additional Gas sold (MMcfd) - industrial
|
11.1
|
7.8
|
42%
|
|
9.8
|
7.2
|
36%
|
|
Additional Gas sold (MMcfd) - power
|
46.4
|
48.3
|
(4%)
|
|
45.3
|
37.4
|
21%
|
|
Additional Gas sold (MMcfd) - total
|
57.5
|
56.1
|
2%
|
|
55.1
|
44.6
|
24%
|
|
Average price per mcf (US$) - industrial
|
9.21
|
10.47
|
(12%)
|
|
9.62
|
10.10
|
(5%)
|
|
Average price per mcf (US$) - power
|
3.55
|
2.76
|
28%
|
|
3.03
|
2.69
|
13%
|
Chairman & CEO's Letter to Shareholders
Orca Exploration is encouraged by many positive accomplishments in Q3
2012. This is good news as we continue to navigate our way through the
most challenging year in Orca's history. With the commissioning of our
new SS-11 well the Songo Songo field has never been in better
operational shape from the perspective of wellbore integrity and
reliability. We continue to deliver gas at capacity to hungry markets.
We posted record financial results in Q3 and we continue to make
tangible progress in recovering past due payments from TANESCO.
We are also encouraged that the Government is delivering on the pipeline
infrastructure project. The long awaited expansion of pipeline and
facilities capacity has begun and we are working to take the Company to
the next level in production. Orca is privileged to be playing a key
role in meeting Tanzania's near-to-medium term energy strategy
objectives.
However we continue to face substantial uncertainties that still need
resolution. It is Orca's highest priority to remove those risks that
cast a shadow over our operations in Tanzania. To do this we will
continue to work closely with the Government towards a full and fair
resolution. During the quarter no real progress was made in concluding
and documenting the issues agreed in principle with the Government
Negotiating Team ("GNT") in July. At that time we had reached an
agreement with the GNT on a number of major points to resolve critical
issues. Recognising that resolution of these issues is a major
impediment to committing to further field development in Tanzania, Orca
has asked the Ministry of Energy and Mines ("MEM") to foster the
necessary collaboration to resolve these matters and bring them to a
conclusion. Based on the progress made to date on TANESCO payments,
Orca continues to believe that MEM has the vision and commitment to
facilitate a successful completion of the GNT process.
Resolving uncertainties
TANESCO payments are foremost in the minds of our shareholders and
management. We are pleased to report that as a result of close
collaboration with MEM and new TANESCO management, progress has been
made in reducing TANESCO past due accounts. The Company has received
US$22.7 million over the past five months and the arrears have been
reduced to US$21.7 million. We continue to work closely with the
Government towards a full resolution. The Company received US$13.2
million from the state utility during Q3 and a further US$9.5 million
since the end of the quarter. At the end of Q3, the TANESCO receivable
stood at US$31.2 million (of which US$26.8 million was in arrears), up
5% from US$29.6 million (US$25.6 million in arrears) at the end of Q2.
A viable state utility is a critical component to delivering Tanzania's
industrialization and economic growth strategy going forward. An
emergency power plan was established a number of years ago as a result
of the lack of infrastructure capacity in Tanzania to move additional
natural gas to fire much needed power plants. The plan placed TANESCO
in the untenable position of having to purchase both high cost
independently generated power and large volumes of high cost liquid
fuels to generate power without offsetting increases in power prices.
There is a cost of service study ongoing by the Tanzanian regulator,
EWURA, the result of which is expected to be recommendations to
increase power prices in early 2013. Power prices reflecting the real
cost of service in the country, together with a changing fuel mix
weighted towards natural gas, are expected to restore the state utility
to a viable business model by the time the pipeline expansion is
commissioned in 2014.
Draft natural gas policy review
On 1 November 2012, the Government of Tanzania issued a draft natural
gas policy for review and consultation with stakeholders. The new
policy contemplates a restructuring of Tanzania Petroleum Development
Corporation ("TPDC") to participate across the upstream, mid-stream and
downstream sectors of the industry through a national oil company and
to regulate the industry through a new regulatory body.
The Government's stated objective for mid-stream and downstream sector
in the draft policy is to promote the development of facilities for
natural gas processing, liquefaction, transportation, storage and
distribution to ensure reliability of supply. The draft policy
contemplates a restructured TPDC acting as a national aggregator of
natural gas, owning and managing natural gas infrastructure.
The draft policy does not contemplate market driven gas prices, but
rather a government role in establishing "an appropriate pricing
structure" which can both encourage economic use of the system
capacities and as well provide incentives for promoting investment.
The draft policy also contemplates strategic involvement by the
Government in the LNG value chain and the promotion of efficient LNG
production as well as management of natural gas revenues, local
content, community & social responsibilities and issues of transparency
and accountability.
The Oil and Gas Association of Tanzania ("OGAT"), of which Orca is a
member, has prepared a submission on behalf of industry on the draft
policy. A copy of the draft policy is available on the Company's
website. It is possible that the final terms of the draft Natural Gas
Policy may vary from the initial draft and the Company is monitoring
developments closely as the draft policy as originally proposed could
have a significant effect on the Company's business operations.
Financial results
To meet constant high demand, Orca continued to operate at maximum plant
and pipeline capacity. The Company delivered Additional Gas sales
volumes averaging 57.5 MMcfd for the quarter, up 6% over Q2 (Q3 2011:
56.1 MMcfd). A 23% increase in Industrial Gas sales volumes and a 27%
increase in Power Gas prices, together with a higher revenue share from
cost recovery, combined to deliver record funds from operations before
working capital changes of US$14.4 million (US$0.41 per share) for the
quarter. This represents a 44% increase over Q2 (US$9.9 million or
US$0.28 per share) and 170% over Q3 2011 (US$5.3 million or US$0.15 per
share). Management currently expects the Songo Songo Production Sharing
Agreement ("PSA") cost pools to be fully recovered by year end. If the
cost pools had been fully recovered at the beginning of the quarter,
funds from operations for the quarter would have been approximately
US$8.0 million (US$0.23 per share), a result of the higher revenue
interest of TPDC in the PSA after cost recovery. Profit after tax for
the quarter was down 75% to US$1.3 million or US$0.04 per share over Q2
(Q2 2012: US$5.2 million or US$0.15 per share) as a result of writing
off US$7.5 million in costs associated with the La Tosca Italy
exploration well.
Average Power Gas sales prices were up over Q2 to US$3.55/Mcf from
US$2.80/Mcf, a result of higher prices provided under the Portfolio Gas
Sales Agreement with TANESCO. Weaker liquids fuels prices drove a 9%
reduction in Industrial Gas sales prices to US$9.21/Mcf from
US$10.14/Mcf in Q2.
The Company remains in a strong financial position with working capital
at the end of the quarter of US$37.7 million including cash of US$23.3
million, down 2% and up 15% respectively over Q2 2012. The cost of
drilling of the SS-11 well was offset by the drawdown of US$6.0 million
in bank financing and the receipt of some TANESCO payments during the
quarter.
Bank financing
During the quarter, the Company closed a US$10 million secured bridge
loan facility with a Tanzania bank to assist in working capital whilst
the TANESCO payment issues are being resolved. The facility has a term
of 18 months and is to be repaid in equal installments beginning in
March 2013. During the quarter, the Company drew US$6.0 million under
the facility. Once the TANESCO payments and GNT issues are resolved,
the Company will be in a position to proceed with a reserve-backed
facility to finance development. Depending on the time required for
resolution of these issues, the Company may secure other financing to
support its operations.
Tanzania operations
At the end of the quarter Orca brought the SS-11 production well
onstream serving to maintain and strengthen deliverability of the
Company's Songo Songo gas production. SS-11 was drilled as a
directional well from onshore Songo Songo Island and was completed in
May 2012. SS-11 is currently producing approximately 38 million cubic
feet per day ("MMcfd") of natural gas through a six-inch diameter
Technip Coflexip® pipe laid along the seabed to achieve an efficient
natural cooling of the gas stream prior to the plant inlet.
The installation involved developing innovative solutions to a number of
engineering challenges which were met entirely by local Tanzanian
contractors and suppliers who delivered the project on budget and in
approximately one-third the time of other solutions. The project
achieved some significant milestones in Tanzania, including the first
offshore heavy lift achieved in East Africa and the first shallow water
application of the technically advanced Coflexip® pipe in East Africa.
SS-11 is an important addition to the production wellbore inventory of
Songo Songo. The production equipment originally installed in the SS-9,
SS-5, SS-4 and SS-3 wells drilled by TPDC between 1976 and 1983 has
reached the end of its useful life. The SS-10 well was drilled by the
Company in 2007 and is currently producing approximately 40 MMcfd. With
SS-11 now onstream Orca has taken the SS-9 well off production and
suspended it as planned. It is anticipated that production from the new
SS-11 well can be increased to over 40 MMcfd with a debottlenecking of
the gas gathering infrastructure, expected to be completed over the
next number of months.
The SS-9 well, which was producing approximately 30 MMcfd, was planned
to be shut in and used only as spare capacity until SS-12 could be
drilled. During the quarter, rising casing annulus pressures resulting
from a tubing leak dictated that SS-9 be permanently suspended. In
connection with the SS-9 suspension, the Company assessed the integrity
of SS-3 and SS-4, which were producing a total of approximately 18
MMcfd. With a similar rise in casing annulus pressure suggesting a
tubing leak, a decision was taken to suspend SS-3 to ensure continued
safe operations in the field. The Company plans to make up the
production shortfall with additional volumes from SS-10 and SS-11. As a
result no material change in field production levels of approximately
101 MMcfd is currently anticipated. There will be, however, no
redundant capacity in the facility or pipeline until additional wells
can be drilled in the field and facilities expanded.
Plans to drill an additional development well, SS-12, and an appraisal
well at Songo Songo West were placed on hold in mid-2012. Until the
outstanding TANESCO receivables have been paid and the re-negotiation
of certain terms of the Songo Songo Production Sharing Agreement with
the Government and related issues arising from the GNT have been fully
resolved, Orca will be unable to proceed with drilling either of these
wells.
Pipeline construction has commenced
On 8 November, His Excellency Jakaya Kikwete, President of the United
Republic of Tanzania, formally commissioned the start of construction
of the Mnazi Bay to Dar es Salaam Gas Pipeline Project, which will tie
into expanded Songo Songo facilities onshore at Somanga Funga. The
Government has stated that the 532km pipeline and its associated
facilities are expected to be completed and commissioned in 18 months.
This US$1.2 billion infrastructure expansion project is expected to
provide Orca with much needed process and pipeline capacity expansion
at Songo Songo. The Company had initial technical consultations with
the project manager and Songo Songo partner, TPDC, in mid-November. The
Company's current objective is to have approximately 200 MMcfd of total
gas (approximately 160 MMcfd Additional Gas sales) onstream by the end
of 2014 and a field development plan is being prepared for discussion
with TPDC. In addition to the outstanding matters of TANESCO payments
and GNT issues, the Company has yet to establish any commercial or
contractual basis for the processing, transportation or sale of these
incremental volumes. All these matters will be required to be resolved
prior to our commitment to proceed.
As the Company reported over the past several quarters, power supply is
an acute issue for Tanzania aggravated by the lack of rains to fill
reservoirs for hydro generation. The Government issued an order in
August 2012 to the Company to redirect all gas volumes (including sales
to Industrial Gas customers) to TANESCO until 31 December 2012 to aid
in emergency power generation. The Company responded immediately and in
collaboration with the Government, identified a solution which provided
TANESCO with sufficient volumes of gas without compromising the
Company's Industrial Gas customers.
Italian operations
In the Longastrino Block in the Po Valley region of Northern Italy the
La Tosca farm-in well was spud on 7 August 2012. It reached total depth
of 2,335 metres and was plugged and abandoned in early September having
encountered gas shows. The drilling indicated a more limited reservoir
sand development than expected from earlier extrapolation of data from
nearby wells. The partners concluded that the data did not provide a
sufficiently strong economic case to warrant well completion and
testing. Total cost of the well to the Company was US$7.5 million,
which was written off during the quarter. As a result of the drilling,
the Company has earned a 70% working interest and once approved as the
new operator, Orca intends to review the technical and drilling data to
determine whether to continue exploration on the block.
During the quarter, the Elsa offshore Italy opportunity cleared an
important regulatory hurdle. Legislative Decree 83/2012 (the "Decree"),
published on 26 June 2012 was approved by both houses of the Italian
Parliament with no substantial modifications. On 12 August 2012, the
Decree became law following publication in the Italian Official
Journal. The new law modifies restrictions on offshore oil and gas
exploration and production originally introduced by DLGS 128/2010 in
August 2010. Petroceltic plc, the operator of the permit has stated
that the new legislation removes the existing uncertainty concerning
exploration, development and production activities in Italian waters
clearing the way for a new application.
Moving forward
Orca remains firmly committed to Tanzania and the development of the
country's natural gas resources. In our continued commitment to
Tanzania, we are strengthening our in country management team.
Shareholders, and in particular those who have been with the Company
since its predecessors, will be pleased to know we have appointed David
K. Roberts as Orca's Vice President Operations based in Dar es Salaam.
From 1999 to 2006 Mr. Roberts was instrumental in managing PanOcean
Energy's growth in Gabon from 400 barrels of oil per day ("bpd") to
20,000 bpd.
Against a backdrop of solid operating and financial performance Orca is
making tangible progress on the issues that have interrupted the
Company's exploration and development program in Tanzania. In the past
few months we have demonstrated that Orca and the Government of
Tanzania can collaborate successfully in moving towards solutions that
are aligned with our common interests. We fully intend to continue on
this path and build on this positive working relationship.
Condensed Consolidated Interim Statement of Comprehensive Income/Loss
(unaudited)
ORCA EXPLORATION GROUP INC.
| |
|
|
|
|
|
|
|
(Figures in US$'000 except per share amounts)
|
|
|
THREE MONTHS ENDED
|
|
NINE MONTHS ENDED
|
|
NOTE
|
|
30 Sep 2012
|
30 Sep 2011
|
|
30 Sep 2012
|
30 Sep 2011
|
|
REVENUE
|
|
|
22,425
|
10,457
|
|
56,545
|
28,393
|
|
Cost of sales
|
|
|
|
|
|
|
|
|
Production and distribution expenses
|
|
|
(1,497)
|
(1,800)
|
|
(4,624)
|
(4,009)
|
|
Depletion expense
|
|
|
(2,324)
|
(2,647)
|
|
(6,279)
|
(5,957)
|
|
|
|
|
18,604
|
6,010
|
|
45,642
|
18,427
|
|
General and administrative expenses
|
|
|
(4,391)
|
(4,399)
|
|
(12,322)
|
(10,736)
|
|
Exploration asset impairment
|
3
|
|
(7,496)
|
-
|
|
(7,496)
|
-
|
|
Net finance costs
|
|
|
(407)
|
(322)
|
|
(689)
|
(1,031)
|
|
Profit before taxation
|
|
|
6,310
|
1,289
|
|
25,135
|
6,660
|
|
Taxation
|
2
|
|
(5,044)
|
(1,343)
|
|
(12,310)
|
(3,941)
|
|
Profit/(loss) after taxation and comprehensive income
|
|
|
1,266
|
(54)
|
|
12,825
|
2,719
|
| |
|
|
|
|
|
|
|
|
EARNINGS/(LOSS) PER SHARE
|
|
|
|
|
|
|
|
|
Basic (US$)
|
|
|
0.04
|
(0.00)
|
|
0.37
|
0.08
|
|
Diluted (US$)
|
|
|
0.04
|
(0.00)
|
|
0.36
|
0.08
|
Condensed Consolidated Interim Statement of Financial Position
(unaudited)
ORCA EXPLORATION GROUP INC.
|
(Figures in US$'000)
|
|
|
AS AT
|
|
NOTE
|
|
30 Sep 2012
|
31 Dec 2011
|
|
ASSETS
|
|
|
|
|
|
Current assets
|
|
|
|
|
|
Cash and cash equivalents
|
|
|
23,289
|
34,680
|
|
Trade and other receivables
|
|
|
62,285
|
40,348
|
|
Taxation receivable
|
|
|
15,078
|
5,880
|
|
Prepayments
|
|
|
499
|
302
|
|
|
|
|
101,151
|
81,210
|
|
Non-current assets
|
|
|
|
|
|
Exploration and evaluation assets
|
3
|
|
5,451
|
2,921
|
|
Property, plant and equipment
|
4
|
|
103,383
|
67,713
|
|
|
|
|
108,834
|
70,634
|
|
Total assets
|
|
|
209,985
|
151,844
|
| |
|
|
|
|
|
EQUITY AND LIABILITIES
|
|
|
|
|
|
Current liabilities
|
|
|
|
|
|
Trade and other payables
|
|
|
50,753
|
22,801
|
|
Bank loan
|
7
|
|
5,800
|
-
|
|
Taxation payable
|
|
|
6,867
|
2,403
|
|
|
|
|
63,420
|
25,204
|
|
Non-current liabilities
|
|
|
|
|
|
Deferred income taxes
|
2
|
|
19,285
|
15,194
|
|
Deferred additional profits tax
|
2
|
|
7,076
|
4,787
|
|
|
|
|
26,361
|
19,981
|
|
Total liabilities
|
|
|
89,781
|
45,185
|
| |
|
|
|
|
EQUITY
|
|
|
|
|
Capital stock
|
6
|
|
84,610
|
84,610
|
|
Contributed surplus
|
|
|
6,988
|
6,268
|
|
Accumulated income
|
|
|
28,606
|
15,781
|
|
|
|
|
120,204
|
106,659
|
|
Total equity and liabilities
|
|
|
209,985
|
151,844
|
Condensed Consolidated Interim Statement of Cash Flows (unaudited)
ORCA EXPLORATION GROUP INC.
| |
|
|
|
|
|
|
(Figures in US$'000)
|
|
THREE MONTHS ENDED
|
|
NINE MONTHS ENDED
|
|
NOTE
|
30 Sep 2012
|
30 Sep 2011
|
|
30 Sep 2012
|
30 Sep 2011
|
|
CASH FLOWS FROM OPERATING ACTIVITIES
|
|
|
|
|
|
|
|
Profit after taxation
|
|
1,266
|
(54)
|
|
12,825
|
2,719
|
|
Adjustment for:
|
|
|
|
|
|
|
| |
Depletion and depreciation
|
4
|
2,393
|
2,741
|
|
6,549
|
6,142
|
| |
Exploration assets impairment
|
3
|
7,496
|
-
|
|
7,496
|
-
|
| |
Stock-based compensation
|
|
80
|
493
|
|
701
|
403
|
| |
Deferred income taxes
|
|
2,019
|
718
|
|
4,091
|
1,406
|
| |
Deferred additional profits tax
|
|
900
|
1,158
|
|
2,289
|
1,946
|
| |
Interest income
|
|
(2)
|
(1)
|
|
(4)
|
(5)
|
| |
Unrealised foreign exchange loss
|
|
227
|
268
|
|
303
|
951
|
|
|
|
14,379
|
5,323
|
|
34,250
|
13,561
|
|
(Increase) in trade and other receivables
|
|
(11,086)
|
(8,802)
|
|
(22,577)
|
(14,120)
|
|
(Increase)/decrease in taxation receivable
|
|
(2,293)
|
559
|
|
(9,198)
|
(57)
|
|
(Increase)/decrease in prepayments
|
|
342
|
278
|
|
(197)
|
(102)
|
|
Increase in trade and other payables
|
|
7,653
|
779
|
|
14,688
|
4,582
|
|
Increase in taxation payable
|
|
93
|
(594)
|
|
4,464
|
(684)
|
|
Net cash flows from operating activities
|
|
9,088
|
(2,457)
|
|
21,430
|
3,181
|
|
CASH FLOWS USED IN INVESTING ACTIVITIES
|
|
|
|
|
|
|
|
Exploration and evaluation expenditures
|
|
(5,469)
|
(1,016)
|
|
(10,026)
|
(1,554)
|
|
Property, plant and equipment expenditures
|
|
(9,564)
|
(2,909)
|
|
(42,219)
|
(5,320)
|
|
Interest received
|
|
2
|
1
|
|
4
|
5
|
|
Proceeds from sale of vehicle
|
|
-
|
-
|
|
-
|
5
|
|
Increase in trade and other payables
|
|
3,413
|
152
|
|
13,817
|
1,012
|
|
Net cash used in investing activities
|
|
(11,618)
|
(3,772)
|
|
(38,424)
|
(5,852)
|
|
CASH FLOWS FROM FINANCING ACTIVITIES
|
|
|
|
|
|
|
|
Bank loan proceeds
|
|
5,800
|
-
|
|
5,800
|
-
|
|
Net cash from financing activities
|
|
5,800
|
-
|
|
5,800
|
-
|
|
Increase in cash and cash equivalents
|
|
3,270
|
(6,229)
|
|
(11,194)
|
(2,671)
|
|
Cash and cash equivalents at the beginning of the period
|
|
20,194
|
48,993
|
|
34,680
|
45,519
|
|
Effect of change in foreign exchange
|
|
(175)
|
(132)
|
|
(197)
|
(216)
|
|
Cash and cash equivalents at the end of the period
|
|
23,289
|
42,632
|
|
23,289
|
42,632
|
Condensed Consolidated Interim Statement of Changes in Shareholders'
Equity (unaudited)
ORCA EXPLORATION GROUP INC.
| |
|
|
|
|
|
(US'000)
|
CAPITAL STOCK
|
CONTRIBUTED SURPLUS
|
ACCUMULATED INCOME
|
TOTAL
|
|
Balance as at 1 January 2011
|
85,100
|
5,288
|
7,795
|
98,183
|
|
Stock based compensation
|
-
|
661
|
-
|
661
|
|
Total comprehensive income for the period
|
-
|
-
|
2,719
|
2,719
|
|
Balance as at 30 September 2011
|
85,100
|
5,949
|
10,514
|
101,563
|
| |
|
|
|
|
|
(US'000)
|
CAPITAL STOCK
|
CONTRIBUTED SURPLUS
|
ACCUMULATED INCOME
|
TOTAL
|
|
Note
|
6
|
|
|
|
|
Balance as at 1 January 2012
|
84,610
|
6,268
|
15,781
|
106,659
|
|
Stock based compensation
|
-
|
720
|
-
|
720
|
|
Total comprehensive income for the period
|
-
|
-
|
12,825
|
12,825
|
|
Balance as at 30 September 2012
|
84,610
|
6,988
|
28,606
|
120,204
|
Orca Exploration is an international public company engaged in natural
gas exploration, development and supply in Tanzania and oil appraisal
and gas exploration in Italy. Orca Exploration trades on the TSXV under
the trading symbols ORC.B and ORC.A.
Neither the TSX Venture Exchange nor its Regulation Service Provider (as
that term is defined in the policies of the TSX Venture Exchange)
accepts responsibility for the adequacy or accuracy of this release.
Forward Looking Statements
This press release contains forward-looking statements. More
particularly, this press release contains statements concerning, but
not limited to, anticipated timing of completion and commissioning of
pipeline in Tanzania and its associated facilities and the Company's
plans to increase deliverability; the expected amount and timing of
increased deliverability; anticipated effect of the infrastructure
expansion project on Orca Exploration; the Company's plans to review
technical and drilling data to determine whether or not to continue
exploration on the Longastrino exploration block; the Company's
progress in recovering past due payments from TANESCO and the Company's
plans to work closely with the Government towards a resolution; Orca
Exploration's expectations regarding the successful completion of the
GNT process; anticipated results from the cost of service study ongoing
by the Tanzanian regulator, EWURA; terms of the draft natural gas
policy and the anticipated effect of the draft policy on the Company's
business operations; expectations regarding timing of full recovery of
the Songo Songo Production Sharing Agreement cost pools; terms of
secured bridge loan facility with a Tanzania bank; the Company's plans
to proceed with a reserve-backed facility to finance development once
the TANESCO payments and GNT issues are resolved; the Company's plans
to secure other financing to support its operations; expectations
regarding ability to increase production from the new SS-11 well and
the anticipated amount thereof; anticipated timing of completion of a
debottlenecking of the gas gathering infrastructure; the Company's
plans to make up a production shortfall with additional volumes from
SS-10 and SS-11 wells; anticipated production volumes; and the
Company's strategic plans.
These forward-looking statements involve substantial known and unknown
risks and uncertainties, certain of which are beyond Orca Exploration's
control, including, but not limited to, risk that the Company will not
be able to fulfill its obligations; failure of counterparties to
perform on contracts; failure to successfully negotiate contracts; the
impact of general economic conditions in the areas in which Orca
Exploration operates; civil unrest; industry conditions; changes in
laws and regulations including the adoption of new environmental laws
and regulations and changes in how they are interpreted and enforced;
increased competition; the lack of availability of qualified personnel
or management; fluctuations in commodity prices; foreign exchange or
interest rates; stock market volatility; competition for, among other
things, capital, drilling equipment and skilled personnel; failure to
obtain required equipment for drilling; delays in drilling plans;
failure to obtain expected results from drilling of wells; changes in
laws; imprecision in reserve estimates; the production and growth
potential of the Company's assets; obtaining required approvals of
regulatory authorities; risks associated with negotiating with foreign
governments; failure to obtain required funding; and ability to access
sufficient capital. In addition there are risks and uncertainties
associated with oil and gas operations, therefore Orca Exploration's
actual results, performance or achievement could differ materially from
those expressed in, or implied by, these forward-looking estimates and,
accordingly, no assurances can be given that any of the events
anticipated by the forward-looking estimates will transpire or occur,
or if any of them do so, what benefits that Orca Exploration will
derive therefrom.
Such forward-looking are based on certain assumptions made by Orca
Exploration in light of its experience and perception of historical
trends, current conditions and expected future developments, as well as
other factors Orca Exploration believes are appropriate in the
circumstances, including, but are not limited to, infrastructure
capacity; commodity prices will not deteriorate significantly; the
ability of Orca Exploration to obtain equipment in a timely manner to
carry out exploration, development and exploitation activities; future
capital expenditures; availability of skilled labour; timing and amount
of capital expenditures; uninterrupted access to infrastructure; the
impact of increasing competition; conditions in general economic and
financial markets; effects of regulation by governmental agencies; that
the Company will have sufficient cash flow, debt or equity sources or
other financial resources required to fund its capital and operating
expenditures and requirements as needed; current or, where applicable,
proposed industry conditions, laws and regulations will continue in
effect or as anticipated as described herein; and future capital
expenditures.
The forward-looking statements contained in this press release are made
as of the date hereof and Orca Exploration undertakes no obligation to
update publicly or revise any forward-looking statements or
information, whether as a result of new information, future events or
otherwise, unless so required by applicable securities laws
SOURCE: Orca Exploration Group Inc.